Filing of a Request for Reconsideration of a Decision Concerning a Contract Award Is Untimely
B-186124
Oct 22, 1976
Skip to Highlights
Highlights
A company requested reconsideration of a decision which denied its protest concerning the Defense Personnel Support Center's proposed award to another firm of a requirements contract for hydralazine hydrochloride tablets. The protester failed to file its pro test to GAO within the required time period after being advised of the decision. The request must be denied as untimely.