Request for Correction of Mistake in Bid

B-183717 Jun 02, 1975
Jump To:
Skip to Highlights

Highlights

The contractor requested permission to correct its bid price due to an alleged error made in computing the bid. Correction of the mistake in bid, alleged after contract award, was not permitted since the contracting officer was not on actual or constructive notice of the alleged mistake prior to award. The bid was only about 9 percent less than the next low bid, and there was close proximity in the range of all bids.