Untimely Protest Against Allegedly Defective Specifications

B-183530: Jul 2, 1975

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A company protested that a solicitation was defective because it allowed unbalanced bidding. The protest alleging defective specifications was untimely and not for consideration since it was filed after closing date for receipt of proposals.

Nov 16, 2017

  • HBI-GF, JV
    We deny the protest.
    B-415036
  • Epsilon Systems Solutions, Inc.
    We dismiss the protest because it raises a matter of contract administration over which we do not exercise jurisdiction.
    B-414410.4

Nov 15, 2017

Nov 14, 2017

Nov 9, 2017