The agency requested a decision concerning an error the contractor alleged was made during telegraphic transmission. The bid was transmitted by personnel and equipment under the contractor's control, and there was no evidence of how the mistake occurred or that the price received by the agency was not the intended bid. The contractor's request for contract modification was denied.