Skip to main content

Claim for Proposal Preparation Costs

B-182979 Mar 10, 1978
Jump To:
Skip to Highlights

Highlights

A company's claim for proposal preparation costs was based on decisions that a contract award was improper. The claim was denied because it was not reasonably certain that the claimant would have received the award, if not for improper agency action, since its price exceeded the statutory cost limitation, and it was difficult to predict what technical or price changes other offerors would have made.

Downloads

GAO Contacts

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries