Skip to main content

B-178981, SEP 25, 1973

B-178981 Sep 25, 1973
Jump To:
Skip to Highlights

Highlights

RELATING TO CONTRACT PAY ITEMS WHICH WERE DELIVERED SUBSEQUENT TO THE SPECIFIED CONTRACT DELIVERY DATE. IS NOT ALLOWABLE. EVANS: THIS IS IN RESPONSE TO YOUR LETTER OF JUNE 21. REQUESTING AN ADVANCE DECISION WHETHER THE GENERAL ELECTRIC COMPANY (GE) IS ENTITLED TO PRICE ESCALATION UNDER CLAUSE 43 (ADJUSTMENT OF PRICES FOR LABOR AND MATERIAL) OF CONTRACT NO. THE CLAIM IS RELATED TO CONTRACT PAY ITEMS WHICH WERE DELIVERED SUBSEQUENT TO THE SPECIFIED CONTRACT DELIVERY DATE. WE ARE ADVISED. NO EXCUSABLE DELAYS APPLICABLE TO THE ITEMS COVERED BY THE INVOICES HAVE BEEN CLAIMED BY GE. THE CASES STAND FOR THE PROPOSITION THAT PRICE ESCALATION IS TO BE COMPUTED ON THE BASIS OF THE RATES IN EFFECT AS OF THE CONTRACTUALLY REQUIRED DELIVERY DATE.

View Decision

B-178981, SEP 25, 1973

ADVANCE DECISION DENYING PRICE ESCALATION TO GENERAL ELECTRIC COMPANY UNDER CLAUSE 43 (ADJUSTMENT OF PRICES FOR LABOR AND MATERIAL) OF CONTRACT NO. DA-40-058-CIVENG-66-105, RELATING TO CONTRACT PAY ITEMS WHICH WERE DELIVERED SUBSEQUENT TO THE SPECIFIED CONTRACT DELIVERY DATE. PRICE ESCALATION FOR PERIODS OF UNEXCUSED DELAY, BASED UPON RATES IN EFFECT AFTER THE REQUIRED DELIVERY DATE, IS NOT ALLOWABLE.

TO MR. T. A. EVANS:

THIS IS IN RESPONSE TO YOUR LETTER OF JUNE 21, 1973, WITH ENCLOSURES, REQUESTING AN ADVANCE DECISION WHETHER THE GENERAL ELECTRIC COMPANY (GE) IS ENTITLED TO PRICE ESCALATION UNDER CLAUSE 43 (ADJUSTMENT OF PRICES FOR LABOR AND MATERIAL) OF CONTRACT NO. DA-40-058-CIVENG-66 105. THE CLAIM IS RELATED TO CONTRACT PAY ITEMS WHICH WERE DELIVERED SUBSEQUENT TO THE SPECIFIED CONTRACT DELIVERY DATE. IN THIS CONTEXT, THE QUESTION PRESENTED FOR OUR CONSIDERATION HAS REFERENCE TO THE PROPER RATE OF ESCALATION UNDER THE CLAUSE APPLICABLE TO THE VARIOUS LATE DELIVERIES. WE ARE ADVISED, HOWEVER, THAT THE GOVERNMENT DID NOT EXERCISE ANY RIGHTS UNDER THE CONTRACT DEFAULT CLAUSE ON ACCOUNT OF THE LATE DELIVERIES. NO EXCUSABLE DELAYS APPLICABLE TO THE ITEMS COVERED BY THE INVOICES HAVE BEEN CLAIMED BY GE.

WE AGREE WITH YOUR INTERPRETATION OF OUR DECISIONS 34 COMP. GEN. 565 (1955); 38 COMP. GEN. 826 (1959); AND B-144987, MARCH 17, 1961. IN OUR VIEW, THE CASES STAND FOR THE PROPOSITION THAT PRICE ESCALATION IS TO BE COMPUTED ON THE BASIS OF THE RATES IN EFFECT AS OF THE CONTRACTUALLY REQUIRED DELIVERY DATE, INCLUDING EXCUSABLE DELAYS, AND REMAINS CONSTANT THEREAFTER. PRICE ESCALATION FOR PERIODS OF UNEXCUSED DELAY, BASED UPON RATES IN EFFECT AFTER THE REQUIRED DELIVERY DATE, IS NOT ALLOWABLE. THE RATIONALE IS STATED IN 34 COMP. GEN., SUPRA, AT PAGE 567:

"THE GENERAL ACCOUNTING OFFICE HAS CONSISTENTLY REFUSED TO ALLOW PRICE INCREASES IN CASES SUCH AS THIS EXCEPT WHERE THE DELAY WAS CAUSED BY THE GOVERNMENT OR OTHERWISE WAS EXCUSABLE UNDER THE TERMS OF THE CONTRACT. THE BASIS FOR OUR POSITION IN THIS REGARD IS THAT WE PERCEIVE NO VALID REASON, IN LAW OR EQUITY, FOR REQUIRING THE GOVERNMENT TO ASSUME THE BURDEN OF PRICE INCREASES OCCURRING AFTER THE FINAL DATE DELIVERY WOULD HAVE BEEN MADE BUT FOR THE CONTRACTOR'S OWN FAULT OR NEGLIGENCE. REQUIRE THE GOVERNMENT TO PAY SUCH PRICE INCREASES WOULD PERMIT THE CONTRACTOR TO BENEFIT FROM HIS OWN DELINQUENCY AND WOULD PENALIZE THE GOVERNMENT FOR MINIMIZING THE CONTRACTOR'S LOSS WHICH WOULD HAVE RESULTED HAD THE CONTRACT BEEN TERMINATED BECAUSE OF THE CONTRACTOR'S DEFAULT."

THE INVOICES SUBMITTED BY GE ARE RETURNED HEREWITH.

GAO Contacts

Office of Public Affairs