TO FOSTER WHEELER CORPORATION: FURTHER REFERENCE IS MADE TO YOUR TELEGRAM OF FEBRUARY 3. WAS THOROUGHLY CONSIDERED AND IT WAS CONCLUDED (1) THAT THE STRESS LIMITATION FOR T-1 STEEL COULD BE INCREASED FROM 37. THE INVITATION FOR BIDS WAS REVISED BY ADDENDUM NO. 5 TO REFLECT THOSE CHANGES IN THE TECHNICAL PROVISIONS. IT IS UNDERSTOOD THAT THE CHANGES MEET YOUR OBJECTIONS AND.

B-141914, MAR. 29, 1960

TO FOSTER WHEELER CORPORATION:

FURTHER REFERENCE IS MADE TO YOUR TELEGRAM OF FEBRUARY 3, 1960, PROTESTING CERTAIN REQUIREMENTS OF INVITATION FOR BIDS NO. ENG-23-028 60- 46 ISSUED BY THE CORPS OF ENGINEERS, KANSAS CITY, MISSOURI.

THE DEPARTMENT OF THE ARMY REPORTS THAT YOUR PROTEST, COVERING TWO TECHNICAL ASPECTS OF PRESSURE TANK DESIGN AND FABRICATION USING T-1 STEEL, WAS THOROUGHLY CONSIDERED AND IT WAS CONCLUDED (1) THAT THE STRESS LIMITATION FOR T-1 STEEL COULD BE INCREASED FROM 37,000 PSI TO ONE-HALF THE YIELD STRENGTH OF THE METAL AND (2) THAT THE LIMITATION ON ALLOWABLE THICKNESS OF STEEL COULD BE WAIVED. THE INVITATION FOR BIDS WAS REVISED BY ADDENDUM NO. 5 TO REFLECT THOSE CHANGES IN THE TECHNICAL PROVISIONS. IT IS UNDERSTOOD THAT THE CHANGES MEET YOUR OBJECTIONS AND, THEREFORE, NO FURTHER ACTION BY THIS OFFICE APPEARS NECESSARY.

Oct 13, 2017

Oct 12, 2017

Oct 11, 2017

  • Daekee Global Company, Ltd.
    We dismiss the protest because the protester has not established that it is an interested party.
    B-414899,B-414899.2

Oct 10, 2017

Oct 6, 2017

Oct 5, 2017

Looking for more? Browse all our products here