Air Traffic Control:

Timely Completion of FAA's Standard Terminal Automation Replacement System Software Is at Risk

AIMD-98-41R: Published: Jan 23, 1998. Publicly Released: Feb 24, 1998.

Additional Materials:

Contact:

Joel C. Willemssen
(202) 512-6253
contact@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO reviewed the Federal Aviation Administration's (FAA) Standard Terminal Automation Replacement System (STARS) software, focusing on: (1) the composition, status, and quality of STARS software; and (2) potential risks to timely, successful completion of STARS software.

GAO noted that: (1) STARS is a complex, costly, and software-intensive system that is to replace aging terminal display and processing systems at 171 FAA facilities nationwide; (2) FAA plans to implement STARS in two phases--the Initial System Configuration and the Final System Configuration--between December 1998 and June 2005 at a total development and deployment cost of about $1 billion; (3) there are three primary components of the STARS software: (a) full service (software enabling air traffic control functions); (b) emergency service (software providing backup should the primary system fail); and (c) transition (software for moving from the current environment to STARS); (4) the three components are being developed in a total of four builds; (5) the first build has been developed, while the remaining three are being developed; (6) FAA estimates that STARS software development will cost about $25 million; (7) for a number of reasons, FAA is behind schedule in developing STARS' full service software component; (8) software milestones were originally determined by working backwards from a predetermined date for implementing the initial configuration that was based on when the existing system would no longer be reliable, rather than being estimated as a function of the software development effort; (9) the new/modified full service component is now estimated to be 50 percent larger than the original estimate; (10) Raytheon Electronic Systems was slow in staffing the project; (11) Raytheon introduced a new software development tool that caused delays while staff learned to use this tool; (12) actual productivity rates were lower than projected; (13) Raytheon took longer than expected to specify the software requirements for builds 2 and 3 of the full service component; (14) in an effort to monitor software quality, Raytheon conducted quality assurance audits of software processes and has since resolved all findings resulting from these audits; (15) the development of STARS software entails several risks that are likely to cause further delays; (16) scheduled completion dates for builds 3 and 4 do not reflect previous delays and problems; (17) software requirements have increased since the software development schedule was set; (18) FAA's decision to develop builds 2 and 3 in parallel increases the risks that problems will take longer to correct; (19) in an attempt to remain on schedule, FAA has eliminated some testing requirements; (20) actual software productivity is below even revised goals; and (21) FAA and Raytheon have acknowledged the risks and have risk mitigation efforts under way.

Sep 14, 2016

Sep 2, 2016

Aug 8, 2016

Jul 28, 2016

Jul 13, 2016

Jul 7, 2016

Jun 24, 2016

Jun 21, 2016

May 26, 2016

Looking for more? Browse all our products here