Payment Under Settlement Agreement Between the Army and Storage Technology Corporation
B-233417
Mar 31, 1992
Skip to Highlights
Highlights
The Army has requested an advance decision concerning proposed payment under an agreement between the Defense Supply Service-Washington (DSS-W) and Storage Technology-Corporation (StorageTek) settling a bid protest the filed with the General Services Administration Board Contract Appeals (GSBCA or Board).
We conclude that payment under the agreement should not be made.