B-223959, AUG 28, 1986, 86-2 CPD 238

B-223959 Aug 28, 1986
Jump To:
Skip to Highlights

Highlights

THESE ARE MATTERS WHICH ARE PRIMARILY WITHIN THE BROAD DISCRETION OF THE CONTRACTING OFFICER. THE AIR FORCE SHOULD VERIFY THOSE DOCUMENTS BECAUSE "CONTROL IS MANY TIMES EXERCISED THROUGH BONDING COMPANIES AND BANKS IN THE FORM OF GUARANTEES FOR OTHER COMPANIES.". THE BID OPENING DATE WAS AUGUST 5. PROVIDES THAT SUCH AFFIDAVITS ARE TO BE OBTAINED WHEN THE CONTRACTING OFFICER DETERMINES THAT DISCLOSURE OF AFFILIATED BIDDERS IS NECESSARY TO PREVENT PRACTICES PREJUDICIAL TO FAIR AND OPEN COMPETITION. WE HAVE HELD THAT WHERE THE IFB REQUIRES THE NAMES AND ADDRESSES OF ALL AFFILIATES OF A BIDDER. WHICH ARE MATTERS PRIMARILY WITHIN THE BROAD DISCRETION OF THE CONTRACTING OFFICER. OUR OFFICE DOES NOT REVIEW AFFIRMATIVE DETERMINATIONS OF RESPONSIBILITY UNLESS THERE HAS BEEN A SHOWING THAT THE CONTRACTING OFFICER MAY HAVE ACTED FRAUDULENTLY OR IN BAD FAITH OR THAT DEFINITIVE RESPONSIBILITY CRITERIA HAVE NOT BEEN MET.

View Decision

B-223959, AUG 28, 1986, 86-2 CPD 238

CONTRACTORS - RESPONSIBILITY - DETERMINATION - TIME FOR MAKING DETERMINATION DIGEST: 1. THE FAILURE TO SUBMIT WITH THE BID AN AFFIDAVIT LISTING AFFILIATED FIRMS AS REQUIRED BY THE INVITATION FOR BIDS RELATES TO RESPONSIBILITY RATHER THAN RESPONSIVENESS, AND, THEREFORE, THE INFORMATION MAY BE SUBMITTED AFTER BID OPENING. CONTRACTORS - RESPONSIBILITY - DETERMINATION - REVIEW BY GAO - AFFIRMATIVE FINDING ACCEPTED 2. PROTESTER'S CONTENTION THAT CONTRACTING OFFICER SHOULD VERIFY AFFIDAVITS LISTING AFFILIATED FIRMS CONCERNS BIDDER RESPONSIBILITY AND THE DEPTH OF INVESTIGATION NECESSARY TO MAKE A DETERMINATION THEREON. THESE ARE MATTERS WHICH ARE PRIMARILY WITHIN THE BROAD DISCRETION OF THE CONTRACTING OFFICER. PRIOR TO AWARDING CONTRACT, CONTRACTING OFFICER MUST MAKE AN AFFIRMATIVE DETERMINATION OF PROPOSED AWARDEE'S RESPONSIBILITY' GENERAL ACCOUNTING OFFICE DOES NOT REVIEW CONTRACTING OFFICER'S AFFIRMATIVE DETERMINATION OF RESPONSIBILITY IN THE ABSENCE OF CONDITIONS NOT PRESENT HERE.

ALEMAN FOOD SERVICE, INC.:

ALEMAN FOOD SERVICE INC. PROTESTS THE AWARD OF A FOOD SERVICES CONTRACT BY THE DEPARTMENT OF THE AIR FORCE UNDER INVITATION FOR BIDS (IFB) NO. F16602-86-B-0028 TO ANY BIDDER WHICH FAILED TO SUBMIT NOTARIZED AFFIDAVITS STATING THE NAMES AND ADDRESSES OF THEIR AFFILIATED BUSINESS CONCERNS AS REQUIRED BY THE IFB. ALEMAN ALSO CONTENDS THAT WHERE BIDDERS SUBMITTED AFFIDAVITS, THE AIR FORCE SHOULD VERIFY THOSE DOCUMENTS BECAUSE "CONTROL IS MANY TIMES EXERCISED THROUGH BONDING COMPANIES AND BANKS IN THE FORM OF GUARANTEES FOR OTHER COMPANIES." THE BID OPENING DATE WAS AUGUST 5, 1986.

WE DISMISS THIS PROTEST.

THE FEDERAL ACQUISITION REGULATION (FAR), 48 C.F.R. SEC. 14.201-6(K) (1985), PROVIDES THAT SUCH AFFIDAVITS ARE TO BE OBTAINED WHEN THE CONTRACTING OFFICER DETERMINES THAT DISCLOSURE OF AFFILIATED BIDDERS IS NECESSARY TO PREVENT PRACTICES PREJUDICIAL TO FAIR AND OPEN COMPETITION, SUCH AS MULTIPLE BIDDING. WE HAVE HELD THAT WHERE THE IFB REQUIRES THE NAMES AND ADDRESSES OF ALL AFFILIATES OF A BIDDER, THE FAILURE TO SUBMIT WITH THE BID A LIST OF AFFILIATES RAISES A QUESTION OF RESPONSIBILITY RATHER THAN RESPONSIVENESS, AND, THEREFORE, THE INFORMATION MAY PROPERLY BE SUBMITTED AFTER BID OPENING. MARATHON ENTERPRISES, INC., B-213646, DEC. 14, 1983, 83-2 CPD PARA. 690.

ALEMAN'S CONTENTION THAT THE CONTRACTING OFFICER SHOULD VERIFY THE AFFIDAVITS CONCERNS BIDDER RESPONSIBILITY AND THE DEPTH OF INVESTIGATION NECESSARY TO MAKE A DETERMINATION THEREON, WHICH ARE MATTERS PRIMARILY WITHIN THE BROAD DISCRETION OF THE CONTRACTING OFFICER. SEE MARTIN ELECTRONICS, INC., B-221298, MAR. 13, 1986, 86-1 CPD PARA. 252; CAROLINA WASTE SYSTEMS, INC., B-215689.3, JAN. 7, 1985, 85-1 CPD PARA. 22. THE CONTRACTING OFFICER MUST MAKE AN AFFIRMATIVE DETERMINATION OF A BIDDER'S RESPONSIBILITY PRIOR TO AWARDING THAT BIDDER A CONTRACT. FAR, 48 C.F.R. SEC. 9.103. HOWEVER, OUR OFFICE DOES NOT REVIEW AFFIRMATIVE DETERMINATIONS OF RESPONSIBILITY UNLESS THERE HAS BEEN A SHOWING THAT THE CONTRACTING OFFICER MAY HAVE ACTED FRAUDULENTLY OR IN BAD FAITH OR THAT DEFINITIVE RESPONSIBILITY CRITERIA HAVE NOT BEEN MET. FREUND PRECISION, INC., B-216620, OCT. 23, 1984, 84-2 CPD PARA. 456. NEITHER EXCEPTION IS APPLICABLE HERE.