Skip to main content

B-213953, JAN 9, 1984

B-213953 Jan 09, 1984
Jump To:
Skip to Highlights

Highlights

DIGEST: GAO WILL NOT CONSIDER A PROTEST THAT AN AGENCY SHOULD HAVE EXERCISED A CONTRACT OPTION INSTEAD OF ISSUING A NEW SOLICITATION WHERE THE OPTION IS EXERCISABLE AT THE SOLE DISCRETION OF THE GOVERNMENT. SINCE THIS IS A MATTER OF CONTRACT ADMINISTRATION. THE CONTRACT IS A REQUIREMENTS TYPE FOR WATERTIGHT CLOSURE REPAIRS. AN OPTION IS EXERCISABLE AT THE SOLE DISCRETION OF THE GOVERNMENT. A DECISION NOT TO EXERCISE THE OPTION IS A MATTER OF CONTRACT ADMINISTRATION AND NOT ONE THAT WILL BE CONSIDERED UNDER OUR BID PROTEST PROCEDURES. 83-2 CPD THE PROTEST IS DISMISSED.

View Decision

B-213953, JAN 9, 1984

DIGEST: GAO WILL NOT CONSIDER A PROTEST THAT AN AGENCY SHOULD HAVE EXERCISED A CONTRACT OPTION INSTEAD OF ISSUING A NEW SOLICITATION WHERE THE OPTION IS EXERCISABLE AT THE SOLE DISCRETION OF THE GOVERNMENT, SINCE THIS IS A MATTER OF CONTRACT ADMINISTRATION.

MARDAN MARINE, LTD.:

MARDAN MARINE, LTD. PROTESTS THE DECISION OF THE NAVAL SUPPLY CENTER, PORTSMOUTH, VIRGINIA NOT TO EXERCISE AN OPTION IN CONTRACT NO. N00189-83-D -0153 FOR AN ADDITIONAL 1-YEAR PERFORMANCE PERIOD. THE CONTRACT IS A REQUIREMENTS TYPE FOR WATERTIGHT CLOSURE REPAIRS. THE NAVY DECIDED, FOR VARIOUS REASONS, TO RECOMPETE THE REQUIREMENT.

WHERE AS HERE, AN OPTION IS EXERCISABLE AT THE SOLE DISCRETION OF THE GOVERNMENT, A DECISION NOT TO EXERCISE THE OPTION IS A MATTER OF CONTRACT ADMINISTRATION AND NOT ONE THAT WILL BE CONSIDERED UNDER OUR BID PROTEST PROCEDURES. SENTINEL ELECTRONICS, INC., B-212770, DECEMBER 20, 1983, 83-2 CPD

THE PROTEST IS DISMISSED.

GAO Contacts

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries