Skip to main content

B-189426, AUGUST 9, 1977

B-189426 Aug 09, 1977
Jump To:
Skip to Highlights

Highlights

PROTEST BY SUBCONTRACTOR OF AGENCY DECISION THAT EQUIPMENT TO BE FURNISHED BY SUBCONTRACTOR UNDER PRIME CONTRACT IS UNACCEPTABLE WILL NOT BE CONSIDERED UNDER GAO BID PROTEST PROCEDURES. IT WAS AWARDED A CONTRACT BY MORTON ON DECEMBER 6. IT WAS INFORMED THAT SOME OF THE EQUIPMENT IT PLANNED TO FURNISH WAS UNACCEPTABLE TO THE DEPARTMENT OF AGRICULTURE. VERNITRON'S COMPLAINT IS NOT DIRECTED TO THE AWARD OF A SUBCONTRACT. IT CONCERNS THE DECISION OF THE GOVERNMENT THAT VERNITRON'S EQUIPMENT IS UNACCEPTABLE. THIS IS A MATTER OF CONTRACT ADMINISTRATION BETWEEN THE GOVERNMENT AND THE PRIME CONTRACTOR WHICH IS NOT COGNIZABLE UNDER THE BID PROTEST PROCEDURES. VERNITRON'S PROTEST WILL NOT BE CONSIDERED ON THE MERITS.

View Decision

B-189426, AUGUST 9, 1977

PROTEST BY SUBCONTRACTOR OF AGENCY DECISION THAT EQUIPMENT TO BE FURNISHED BY SUBCONTRACTOR UNDER PRIME CONTRACT IS UNACCEPTABLE WILL NOT BE CONSIDERED UNDER GAO BID PROTEST PROCEDURES.

VERNITRON MEDICAL PRODUCTS:

VERNITRON MEDICAL PRODUCTS (VERNITRON) PROTESTS THE REJECTION BY THE DEPARTMENT OF AGRICULTURE OF EQUIPMENT IT PROPOSED TO FURNISH AS A SUBCONTRACTOR TO JOSEPH MORTON COMPANY, INC. (MORTON), THE PRIME CONTRACTOR FOR CONSTRUCTION WORK TO BE PERFORMED AT THE PLUM ISLAND ANIMAL DISEASE CENTER, PLUM ISLAND, NEW YORK.

ACCORDING TO VERNITRON, IT WAS AWARDED A CONTRACT BY MORTON ON DECEMBER 6, 1976, FOR STERILIZING EQUIPMENT FOR THE PLUM ISLAND PROJECT. SUBSEQUENTLY, IN MAY AND JUNE 1977, IT WAS INFORMED THAT SOME OF THE EQUIPMENT IT PLANNED TO FURNISH WAS UNACCEPTABLE TO THE DEPARTMENT OF AGRICULTURE. VERNITRON OBJECTS TO BOTH THE DEPARTMENT'S DECISION AND ITS REFUSAL TO AFFORD VERNITRON A HEARING ON THE MATTER. VERNITRON ALSO TAKES ISSUE WITH MORTON'S INTERPRETING THE DEPARTMENT'S POSITION AS DISQUALIFYING ALL OF VERNITRON'S EQUIPMENT.

UNDER OUR BID PROTEST PROCEDURES, 4 C.F.R.PART 20 (1977), THIS OFFICE CONSIDERS COMPLAINTS CONCERNING THE AWARD OF GOVERNMENT CONTRACTS. THIS OFFICE ALSO CONSIDERS PROTESTS CONCERNING THE AWARD OF SUBCONTRACTS IN LIMITED CIRCUMSTANCES. OPTIMUM SYSTEMS, INC., 54 COMP.GEN. 767 (1975), 75-1 CPD 166. HOWEVER, VERNITRON'S COMPLAINT IS NOT DIRECTED TO THE AWARD OF A SUBCONTRACT. RATHER, IT CONCERNS THE DECISION OF THE GOVERNMENT THAT VERNITRON'S EQUIPMENT IS UNACCEPTABLE. THIS IS A MATTER OF CONTRACT ADMINISTRATION BETWEEN THE GOVERNMENT AND THE PRIME CONTRACTOR WHICH IS NOT COGNIZABLE UNDER THE BID PROTEST PROCEDURES. LYCO-ZF, B-188037, JANUARY 17, 1977, 77-1 CPD 36; FLAIR MANUFACTURING CORP., B-187870, DECEMBER 14, 1976, 76-2 CPD 486.

IN VIEW OF THE FOREGOING, VERNITRON'S PROTEST WILL NOT BE CONSIDERED ON THE MERITS.

GAO Contacts

Office of Public Affairs