B-210502, FEB 1, 1983
Highlights
DIGEST: QUESTION WHETHER CONTRACTOR IS PERFORMING IN ACCORDANCE WITH CONTRACT TERMS IS A MATTER OF CONTRACT ADMINISTRATION FOR RESOLUTION BY THE CONTRACTING AGENCY. DACW63-82-B-0106 IS PERFORMING IN ACCORDANCE WITH THE SPECIFICATIONS AND OTHER PROVISIONS OF THAT CONTRACT. A QUESTION WHETHER A CONTRACTOR IS PERFORMING IN ACCORDANCE WITH THE CONTRACT TERMS IS A MATTER OF CONTRACT ADMINISTRATION FOR RESOLUTION BY THE CONTRACTING AGENCY AND WILL NOT BE CONSIDERED BY OUR OFFICE. THE PROTEST IS DISMISSED.
B-210502, FEB 1, 1983
DIGEST: QUESTION WHETHER CONTRACTOR IS PERFORMING IN ACCORDANCE WITH CONTRACT TERMS IS A MATTER OF CONTRACT ADMINISTRATION FOR RESOLUTION BY THE CONTRACTING AGENCY, NOT GAO.
CANYON LAKE SANITATION SERVICE:
CANYON LAKE SANITATION SERVICE QUESTIONS WHETHER THE FIRM AWARDED U. S. ARMY CORPS OF ENGINEERS CONTRACT NO. DACW63-82-B-0106 IS PERFORMING IN ACCORDANCE WITH THE SPECIFICATIONS AND OTHER PROVISIONS OF THAT CONTRACT.
A QUESTION WHETHER A CONTRACTOR IS PERFORMING IN ACCORDANCE WITH THE CONTRACT TERMS IS A MATTER OF CONTRACT ADMINISTRATION FOR RESOLUTION BY THE CONTRACTING AGENCY AND WILL NOT BE CONSIDERED BY OUR OFFICE. DYNA COTE IND., INC., B-208543, SEPTEMBER 8, 1982, 82-2 CPD 211.
THE PROTEST IS DISMISSED.