DIGEST: PROTEST IS UNTIMELY WHERE NOT FILED WITH GAO WITHIN TEN WORKING DAYS OF NOTIFICATION OF INITIAL ADVERSE ACTION ON PROTEST FILED WITH AGENCY. KIRBY CONTENDS THAT KARI-VAC'S BID SHOULD HAVE BEEN FOUND NONRESPONSIVE BECAUSE IT INDICATED UNDER THE "PRODUCTION AND INSPECTION POINTS" CLAUSE OF THE SOLICITATION THAT IT WAS THE MANUFACTURER OF TWO ITEMS WHICH ARE IN FACT MANUFACTURED BY ANOTHER FIRM. KARI-VAC ALSO FALSELY CERTIFIED THAT IT WAS A MANUFACTURER OF ALL THE SUPPLIES OFFERED. THE PROTEST IS UNTIMELY. KIRBY MAY HAVE CONTINUED TO PURSUE THE MATTER WITH THE AGENCY THROUGH A MEMBER OF CONGRESS. THE PROTEST IS DISMISSED.

View Decision

B-209043, OCT 4, 1982

DIGEST: PROTEST IS UNTIMELY WHERE NOT FILED WITH GAO WITHIN TEN WORKING DAYS OF NOTIFICATION OF INITIAL ADVERSE ACTION ON PROTEST FILED WITH AGENCY.

KIRBY CENTER:

KIRBY CENTER PROTESTS THE GENERAL SERVICES ADMINISTRATION'S (GSA) AWARD OF A CONTRACT TO KARI-VAC, INC. UNDER SOLICITATION NO. 9FCB-OLK-A A0450/81 FOR FLOOR POLISHING AND SCRUBBING MACHINES, CARPET SHAMPOOERS AND RELATED EQUIPMENT. WE DISMISS THE PROTEST.

KIRBY CONTENDS THAT KARI-VAC'S BID SHOULD HAVE BEEN FOUND NONRESPONSIVE BECAUSE IT INDICATED UNDER THE "PRODUCTION AND INSPECTION POINTS" CLAUSE OF THE SOLICITATION THAT IT WAS THE MANUFACTURER OF TWO ITEMS WHICH ARE IN FACT MANUFACTURED BY ANOTHER FIRM. ACCORDING TO KIRBY, KARI-VAC ALSO FALSELY CERTIFIED THAT IT WAS A MANUFACTURER OF ALL THE SUPPLIES OFFERED. WE CONSIDER THE PROTEST TO BE UNTIMELY FILED.

OUR BID PROTEST PROCEDURES PROVIDE THAT WHERE A PROTEST HAS BEEN FILED INITIALLY WITH THE CONTRACTING AGENCY, ANY SUBSEQUENT PROTEST TO THIS OFFICE MUST BE FILED WITHIN TEN WORKING DAYS OF ACTUAL OR CONSTRUCTIVE KNOWLEDGE OF INITIAL ADVERSE AGENCY ACTION. 4 C.F.R. SEC. 21.2(A) (1982). HERE, KIRBY FILED ITS PROTEST INITIALLY WITH GSA, AND THE AGENCY DENIED THE PROTEST BY LETTER DATED JULY 28, 1982. KIRBY DID NOT FILE ITS PROTEST WITH GAO, HOWEVER, UNTIL SEPTEMBER 14, 1982. CONSEQUENTLY, THE PROTEST IS UNTIMELY.

ALTHOUGH IT APPEARS THAT AFTER GSA'S DENIAL OF ITS PROTEST, KIRBY MAY HAVE CONTINUED TO PURSUE THE MATTER WITH THE AGENCY THROUGH A MEMBER OF CONGRESS, THIS DOES NOT AFFECT THE TEN-DAY REQUIREMENT FOR A TIMELY FILING WITH THIS OFFICE. SEE TSI INCORPORATED - RECONSIDERATION, B-202171, MAY 6, 1981, 81-1 CPD 357.

THE PROTEST IS DISMISSED.