Skip to main content

B-228849, Aug 31, 1987, 87-2 CPD 214

B-228849 Aug 31, 1987
Jump To:
Skip to Highlights

Highlights

PROCUREMENT - Bid Protests - GAO procedures - GAO decisions - Reconsideration DIGEST: A protest filed with the General Accounting Office following adverse agency action on a protest that was untimely filed with the contracting agency is untimely and will not be considered because the initial agency protest was not timely filed. Proto contends that the award was improper since FETCO was listed in the IFB as a component supplier. The protester argues that the solicitation should have prohibited FETCO from bidding. Bids were opened on June 18. If a protest is filed initially with the contracting agency. The subsequent protest filed with our Office must meet two tests in order to be considered timely: (1) it must be filed within 10 working days of the protester's learning of adverse action on the agency protest and (2) the initial protest to the agency must have been timely filed. 4 C.F.R.

View Decision

B-228849, Aug 31, 1987, 87-2 CPD 214

PROCUREMENT - Bid Protests - GAO procedures - GAO decisions - Reconsideration DIGEST: A protest filed with the General Accounting Office following adverse agency action on a protest that was untimely filed with the contracting agency is untimely and will not be considered because the initial agency protest was not timely filed. The fact that the contracting agency considered the protest on the merits does not change this result.

Proto Circuit, Inc.:

Proto Circuit, Inc., protests the award of a contract for circuit card assemblies to Florida Electronics and Transformer Co. (FETCO) under Federal Aviation Administration invitation for bids (IFB) No. DTFA-02-87-B -00577. Proto contends that the award was improper since FETCO was listed in the IFB as a component supplier. Proto contends that because it had to use FETCO's components that firm had an unfair advantage over Proto in the competition. The protester argues that the solicitation should have prohibited FETCO from bidding.

We dismiss the protest as untimely.

Bids were opened on June 18, 1987. Proto filed a protest on the same ground alleged here with the contracting agency after bid opening. The agency denied the protest by letter dated August 5. Proto then filed its protest with out Office on August 21.

A protest against an alleged solicitation impropriety apparent from the face of the solicitation-- in Proto's case, the failure of the IFB to prohibit assembly component suppliers from bidding-- must be filed with either the contracting agency or our Office prior to bid opening. Bid Protest Regulations, 4 C.F.R. Sec. 21.2(a)(1) (1987). If a protest is filed initially with the contracting agency, the subsequent protest filed with our Office must meet two tests in order to be considered timely: (1) it must be filed within 10 working days of the protester's learning of adverse action on the agency protest and (2) the initial protest to the agency must have been timely filed. 4 C.F.R. Sec. 21.2(a)(3). Here, while the first test is met, the second test is not since Proto's protest to the agency was untimely filed after bid opening. Thus, we will not consider Proto's protest to our Office. Ardrox, Inc., B-221241.2, Apr. 30, 1986, 86-1 CPD Para. 421. The fact that the agency considered the untimely protest on the merits does not alter the result, since our timeliness regulations may not be waived by action or inaction of a contracting agency. Hooven Allison, B-224785, Oct. 10, 1986, 86-2 CPD Para. 423.

We dismiss the protest.