Skip to main content

B-234068, May 8, 1989, 89-1 CPD 431

B-234068 May 08, 1989
Jump To:
Skip to Highlights

Highlights

PROCUREMENT - Sealed Bidding - Bid guarantees - Sureties - Acceptability - Information submission PROCUREMENT - Contractor Qualification - Responsibility - Contracting officer findings - Negative determination - GAO review DIGEST: Protester was properly found nonresponsible where it failed to provide sufficient information to permit finding that the individual sureties on its bid bond were acceptable and the record shows the contracting officer's nonresponsibility determination was reasonably based. Construct was the low bidder in the amount of $1. Which was $52. Whichever was less. Bidders were warned that failure to furnish this information could result in rejection of the surety and a determination of nonresponsibility.

View Decision

B-234068, May 8, 1989, 89-1 CPD 431

PROCUREMENT - Sealed Bidding - Bid guarantees - Sureties - Acceptability - Information submission PROCUREMENT - Contractor Qualification - Responsibility - Contracting officer findings - Negative determination - GAO review DIGEST: Protester was properly found nonresponsible where it failed to provide sufficient information to permit finding that the individual sureties on its bid bond were acceptable and the record shows the contracting officer's nonresponsibility determination was reasonably based.

Construct Sun, Inc.:

Construct Sun, Inc., protests the rejection of its bid under invitation for bids (IFB) No. N62467-88-B-0379, issued by the Department of the Navy, for the closure of industrial sludge drying beds and a surge pond at the Naval Air Station in Pensacola, Florida. The Navy rejected Construct's bid on the basis that the two individual sureties on its bid bond failed to submit sufficient proof of ownership and the value of the assets claimed in support of surety net worth.

We deny the protest.

At bid opening, on December 15, 1988, Construct was the low bidder in the amount of $1,567,246, which was $52,509 less than the second low bid of $1,619,755, submitted by Tricil Environmental Response, Inc. The IFB required each bidder to provide a bid guarantee in an amount equal to 20 percent of the bid or $3 million, whichever was less; 20 percent of Construct's bid totaled $313,449. Construct submitted a bid bond naming two individual sureties and, as required by the IFB, provided a completed Affidavit of Individual Surety (SF 28) for each surety. The solicitation further provided that a balance sheet and income statement certified by a certified public accountant (C.P.A.) must be provided for each surety, that ownership of real property listed as an asset on the SF 28 must be evidenced by a title report or abstract, that the net value of the property listed must be substantiated by an independent, certified appraisal, and that an attorney or title company must certify as to whether any liens or encumbrances exist with respect to all listed property. Bidders were warned that failure to furnish this information could result in rejection of the surety and a determination of nonresponsibility.

Construct proposed as individual sureties Virgil Smith and Edgar Powell. While the SF 28s submitted for Mr. Smith and Mr. Powell listed their net worths as $41,469,591 and $12,732,999, respectively, Construct did not submit any documentation establishing the current ownership or value of the claimed assets. Further, while additional documentation concerning the net worth of Mr. Smith was available to the Navy (having been submitted in response to an earlier 1988 Navy solicitation for which Mr. Smith had been proposed as an individual surety), contracting officials nevertheless concluded that the information failed to establish the ownership and value of the assets listed on the SF 28 as required by the solicitation. For example, in this regard, although the financial statement that had been submitted for Mr. Smith, dated August 25, 1988, indicated a net worth of $41,929,707, the C.P.A. who prepared the statement cautioned that it was merely a compilation of information furnished by Mr. Smith, without independent audit or verification.

In addition, the Navy concluded that the integrity and financial responsibility of both sureties was called into question by the results of the agency's review of the Certificates of Sufficiency furnished as part of their SF 28s. That form requires sureties to provide a certificate signed by an officer of a bank or trust company, or by a public official,
in which the officer or official certifies that, based on his personal
investigation, the surety is responsible and the facts stated by the
surety in the SF 28 are true.
The agency reports that contracting
officials were advised by the bank officer who signed Mr. Smith's
Certificate of Sufficiency that she intended merely to verify Mr. Smith's
signature on the affidavit and had no personal knowledge of Mr. Smith's
net worth.
Further, the State of Texas Department of Banking advised that
the Texas institution for which the individual who signed Mr. Powell's
certificate worked was not a bank or trust company under Texas (law and
had been ordered to cease and desist from so representing itself.)

Accordingly, based on the advice of counsel, and without requesting
additional information from Construct or the sureties, the contracting
officer determined that the available evidence did not permit finding the
individual sureties acceptable.
She therefore found Construct
nonresponsible and made award to Tricil on December 30.
Sometime after
the nonresponsibility determination, the contracting officer received
additional information concerning Mr. Smith's assets which she believed
further called into question his acceptability as a surety.

In its protest, Construct disputes the Navy's assessment of the validity
of the Certificates of Sufficiency.
Construct argues in this connection
that the bank officer's duty of personal investigation, as set forth in
the SF 28, did not require her to know the details of Mr. Smith's net
worth and assets, and that the institution whose officer signed Mr.
Powell's Certificate was not required to qualify as a bank or trust
company under state law for the signature to be valid.
Primarily,
however, Construct argues that the Navy acted improperly in finding the
sureties unacceptable without having first asked for additional
information from Construct or the sureties.

Federal Acquisition Regulation (FAR) Sec. 28.202-2(a) requires the
contracting officer to determine the acceptability of individuals proposed
as sureties, and states that the information provided in the SF 28 is
helpful in determining the net worth of proposed individual sureties.
The
contracting officer is not limited to consideration of the information in
the SF 28, however, and may go beyond it where necessary in making his
decision.
J & J Engineering, Inc., B-233463.2, Feb. 13, 1989, 89-1 CPD
Para. 147; Transcontinental Enterprises, Inc., 66 Comp.Gen. 549 (1987),
87-2 CPD Para. 3.
Moreover, the contracting officer is vested with a
wide
degree of discretion and business judgment in determining surety
acceptability, and when he finds a surety unacceptable we will defer to
this judgment unless the protester shows that the determination was
without a reasonable basis.
Cascade Leasing, Inc., B-231848.2, Jan. 10,
1989, 89-1 CPD Para. 20.
Construct has not shown that the contracting
officer's determination here was unreasonable.

First, in requiring that a C.P.A. prepare and certify a balance sheet for
each surety, the solicitation clearly required that the C.P.A. certify to
the accuracy of the amounts; merely relying on figures provided by the
surety without independent verification, as done here for Mr. Smith's
financial statement, does not meet this requirement.
In a similar vein,
whether or not the officer who signed Mr. Smith's Certificate of
Sufficiency was required to possess personal knowledge of the surety's
assets, the fact that the officer advised the Navy that she in fact had no
such knowledge gave the Navy sufficient cause to discount the certificate
as evidence verifying the surety's assets.

Further, the Navy has obtained information that leads it to question
whether Construct has sufficiently established the current value of Mr.
Smith's primary asset-- 100 percent of the stock of the Ace Petroleum
Company, Inc., valued by Smith at $40,897,700-- such that it could be
considered in calculating Mr. Smith's net worth.
In this regard, although
Mr. Smith submitted a geologist's report estimating the extent of the
recoverable oil and gas reserves owned by Ace, it appears from the record
that in fact Ace may own no more than approximately 40 percent of the
reserves upon which the claimed value of Ace was calculated.
At the same
time, the financial statement submitted for Ace, based solely on the
representations of Ace's management (1) lists total assets of $256,613
without consideration of the claimed reserves, but including $83,168 in
unamortized drilling costs and liabilities other than shareholder's equity
of $280,101, resulting in a deficit in shareholders' equity of $23,488,
and (2) lists Ace's income from the sale of oil and gas for the year
ending June 30, 1988, as only $65,980, other income primarily from the
sale of an interest in oil wells as only $61,082, and expenses as
$129,635, thus resulting in a net loss of $2,573.
Since Construct has not
shown that the Ace stock is publicly traded or otherwise has value, and in
view of the speculative character of the corporation's primary asset, we
do not find unreasonable the agency's refusal to consider the stock in
calculating Mr. Smith's assets.

In addition, although Mr. Smith also claimed current ownership of real
property with a value of $661,000, he has provided no proof of ownership
or current value besides 1987 tax notices assessing his property at only
$179,100.
Mr. Smith also failed to provide the required independent
certification by an attorney or title company as to the existence of any
liens or encumbrances on the real property or on the Ace stock.
Finally,
Mr. Smith listed actual liabilities of $176,609 and outstanding bonds of
approximately $3,811,906, an amount exceeding the value of his proven
assets, aside from the Ace petroleum stock.

In these circumstances, since the documents required by the solicitation
to establish the ownership and value of the listed assets have not been
submitted, and Mr. Smith's SF 28 indicates liabilities or potential
liabilities which exceed the substantiated value of his proven assets, we
find that the Navy acted reasonably in determining Mr. Smith unacceptable
as an individual surety.
Both the solicitation and FAR Sec. 28.202
require that at least two acceptable individual sureties execute the
bond.
Since at least one of Construct's two proposed individual sureties
is unacceptable, the contracting officer properly found the firm
nonresponsible.

As for the contracting officer's failure to request additional
information from Construct concerning Mr. Smith, there is no evidence in
the record that, had she requested such information, Construct could have
established the financial acceptability of Mr. Smith.
See generally Hirt
Co., B-230864, June 23, 1988, 88-1 CPD Para. 605.
Although the
solicitation required bidders to furnish with their bids independent
documentary evidence, in addition to the SF 28, establishing ownership,
the extent of encumbrances, and net value of listed assets, Construct made
no attempt to do so. Moreover, although it could have done so in
responding to the agency's report on this protest, Construct still has not
submitted the required documentation.

The protest is denied.

GAO Contacts

Office of Public Affairs