[Protest of Navy Rejection of Bid for Roof Replacement and Repair]

B-260404 Published: May 16, 1995. Publicly Released: May 16, 1995.
Jump To:
Skip to Highlights

Highlights

A firm protested the Navy's rejection of its bid for roof replacement and repair, contending that the Navy improperly rejected its bid as nonresponsive. GAO held that the Navy properly rejected the protester's bid as nonresponsive, since: (1) its bid bond had been inappropriately altered; and (2) it did not show evidence that the surety consented to the alteration. Accordingly, the protest was denied.

Office of Public Affairs

Topics

Bid bondsBid errorsBid rejection protestsBid responsivenessNaval procurementQuestionable procurement chargesRepair contractsSurety bondsU.S. NavyBid evaluation protestsSolicitationsProtestsIntellectual property rightsSealed bidding