[Protest of Navy Rejection of Bid for Pulse Generators]
B-255356
Published: Feb 15, 1994. Publicly Released: Feb 15, 1994.
Skip to Highlights
Highlights
A firm protested the Navy's rejection of its bid for pulse generators, contending that the Navy improperly rejected its bid, since it offered used equipment. GAO held that the Navy properly rejected the protester's bid, since it did not include required information for determining the acceptability of the protester's proposed equipment. Accordingly, the protest was denied.
Office of Public Affairs
Topics
Bid evaluation protestsBid rejection protestsBid responsivenessDescriptive literatureElectronic equipmentEquipment contractsNaval procurementQualified products listTechnical proposal evaluationU.S. NavyBid proposals