Skip to main content

[Claim for Bid and Protest Costs Pursuant to Navy Solicitation]

B-252339.4 Published: Jul 20, 1993. Publicly Released: Jul 20, 1993.
Jump To:
Skip to Highlights

Highlights

A firm requested reimbursement of its bid preparation and protest costs pursuant to a Navy solicitation. GAO held that the protester was not entitled to reimbursement of its bid and protest preparation costs, since the Navy took prompt corrective action. Accordingly, the request was denied.

Office of Public Affairs

Topics

Bid evaluation protestsBid preparation cost claimsBid preparation costsClaims settlementDefective solicitationsLegal feesNaval procurementService contractsSpecifications protests