[Protest of Army Exercise of Contract Option for Ammunition Links]

B-239499 Published: Aug 29, 1990. Publicly Released: Aug 29, 1990.
Jump To:
Skip to Highlights

Highlights

A firm protested the Army's exercise of a contract option for ammunition links, contending that the Army: (1) improperly exercised the option at a price higher than it would have offered; and (2) should have competed the option requirements. GAO held that the Army properly: (1) determined its needs; and (2) exercised the option. Accordingly, the protest was denied.

Full Report

Office of Public Affairs

Topics

Army procurementBid protestsContract optionsEquipment contractsIndustrial mobilizationQuestionable procurement chargesU.S. ArmyMobilization