[Protest of DOE Contractor's Rejection of Offer]
B-237678
Published: Mar 12, 1990. Publicly Released: Mar 12, 1990.
Skip to Highlights
Highlights
A firm protested a Department of Energy prime contractor's rejection of its bid for personnel and testing evaluations, contending that the: (1) contractor improperly concluded that its bid did not meet personnel requirements; and (2) clearance requirements were unreasonable. GAO held that the: (1) contractor properly rejected the protester's bid; and (2) protester untimely protested after bid opening regarding the clearance requirements. Accordingly, the protest was denied in part and dismissed in part.
Full Report
Office of Public Affairs
Topics
Bid rejection protestsProposed employeesService contractsSolicitation specificationsSpecifications protestsSubcontractsUntimely protestsSolicitationsBid evaluation protestsEnergyBid proposalsIntellectual property rightsProtestsSecurity clearancesU.S. NavyEngineering