Skip to main content

[Protest of Army Solicitation as Unduly Restrictive]

B-238541 Published: Feb 23, 1990. Publicly Released: Feb 23, 1990.
Jump To:
Skip to Highlights

Highlights

A firm protested an Army solicitation as unduly restrictive, contending that the Army improperly restricted the procurement to domestic firms. GAO held that the protester untimely filed its protest 8 weeks after initial adverse action on its agency-level protest. Accordingly, the protest was dismissed.

Full Report

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Army procurementBid protest regulationsEquipment contractsSpecifications protestsUntimely protestsBid evaluation protestsU.S. ArmyBid proposalsProtests