[Protest of Army Rejection of Bidder as Nonresponsible]

B-236251 Published: Nov 17, 1989. Publicly Released: Nov 17, 1989.
Jump To:
Skip to Highlights

Highlights

A firm protested the Army's rejection of its bid for sewer repair and replacement, contending that the Army improperly found its sureties unacceptable, since it submitted more than adequate evidence of the value of its sureties' assets. GAO held that the Army reasonably found that the protester failed to provided sufficient information to show that its sureties had sufficient financial resources to meet their bond obligations. Accordingly, the protest was denied.

Full Report

Office of Public Affairs

Topics

Army procurementBid bondsBid evaluation protestsBid rejection protestsBidder responsibilityRepair contractsReal propertyU.S. ArmyFair market value