[Protest of Forest Service Contract Award for Cadastral Surveys]

B-226533 Published: Mar 23, 1987. Publicly Released: Mar 23, 1987.
Jump To:
Skip to Highlights

Highlights

A firm protested a Forest Service contract award for cadastral surveys, contending that: (1) the Forest Service improperly evaluated its bid; (2) the Forest Service unjustly awarded the contract to a higher bidder; and (3) GAO should consider the protest even though it was untimely. GAO held that: (1) the protester untimely filed its protest more than 10 days after it received notice of initial adverse agency action; and (2) it would not consider the protester's untimely protest, which did not raise an issue of widespread significance to the procurement community. Accordingly, the protest was dismissed.

Full Report

Office of Public Affairs

Topics

Bid evaluation protestsBid protest regulationsContract award protestsUntimely protests