[Protest of Forest Service Rejection of Bid as Nonresponsive]

B-223091,B-223156 Published: Aug 11, 1986. Publicly Released: Aug 11, 1986.
Jump To:
Skip to Highlights

Highlights

A firm protested the Forest Service's rejection of its bid for timber purchase as nonresponsive, contending that the Forest Service: (1) did not include a required form in its bid package; and (2) should waive the requirement for the form because of the difference in price between it and the next highest bidder. GAO held that the Forest Service properly rejected the bid as nonresponsive since the requirement was a material term of the sale. Accordingly, the protest was denied.

Office of Public Affairs

Topics

Bid rejection protestsBid responsivenessTimber salesBid evaluation protestsIntellectual property rights