[Protest of Army Decision To Use Less Restrictive Specification for AN/PSM-45 Digital Multimeter]

B-223482 Published: Jul 03, 1986. Publicly Released: Jul 03, 1986.
Jump To:
Skip to Highlights

Highlights

A firm protested an Army decision to relax a procurement's specifications, contending that: (1) the revisions improperly relaxed the existing specification; and (2) the Army should have used a more restrictive specification. GAO held that: (1) the protester failed to show the restrictions were unreasonable; and (2) it would not review a protest that would limit competition. Accordingly, the protest was dismissed.

Office of Public Affairs

Topics