[Protest of DLA Rejection of Bid as Nonresponsive]
B-218477.2
Published: Oct 08, 1985. Publicly Released: Oct 08, 1985.
Skip to Highlights
Highlights
A firm protested the Defense Logistics Agency's rejection of its bid as nonresponsive because it failed to comply with the solicitation specifications. Bid protest regulations require that a protest be filed within 10 working days after the basis of the protest is known. Since this protest was not filed within that timeframe, it was untimely and not for consideration. Accordingly, the protest was dismissed.
Full Report
Office of Public Affairs
Topics
Bid rejection protestsBid responsivenessDefense procurementSolicitation specificationsUntimely protestsBid evaluation protestsSolicitationsProtestsCoal