[Protest of Army Contract Award for Brake Assemblies]

B-219132 Published: Jun 28, 1985. Publicly Released: Jun 28, 1985.
Jump To:
Skip to Highlights

Highlights

A firm protested an Army contract award, contending that, as the lowest responsive and responsible bidder, it should have been awarded the contract. Under bid protest regulations, protests should be filed within 10 days of the receipt of contract award notification. Since this protest was not received within that timeframe, it was untimely and not for consideration. Accordingly, the protest was dismissed.