[Protest Alleging Restrictive Specifications in Army IFB]
B-212592
Published: Sep 21, 1983. Publicly Released: Sep 21, 1983.
Skip to Highlights
Highlights
A firm protested that the specifications in an invitation for bids issued by an Army activity were unduly restrictive. When the Army canceled the solicitation, the firm protested any resolicitation on a sole-source basis. GAO held that the first protest was academic since the solicitation was canceled. In addition, the Army notified GAO that it did not intend to resolicit the procurement. GAO held that its bid protest procedures are not available for challenging future procurements. Accordingly, the protest was dismissed.
Public Inquiries
Topics
Sole source procurementSolicitation cancellationSolicitation specificationsU.S. ArmyBid evaluation protestsResolicitationSpecificationsSolicitationsBid protest regulationsProcurementAviationIntellectual property rightsProtests