[Protest of Army Contract Award]

B-210870.2 Published: Jun 29, 1983. Publicly Released: Jun 29, 1983.
Jump To:
Skip to Highlights

Highlights

A firm protested an Army contract award, contending that the solicitation's specifications were inadequate. Bid protest procedures require that a protest alleging improprieties in a solicitation which are apparent prior to bid opening be filed prior to that date. Since this protest was not filed within the appropriate timeframe, it was untimely and, therefore, would not be considered on its merits. Accordingly, the protest was dismissed.

Full Report

Office of Public Affairs

Topics

Contract award protestsSolicitation specificationsUntimely protestsBid evaluation protestsU.S. ArmySolicitationsBid protest regulationsSpecificationsProtestsImproper award of contractFederal regulationsIntellectual property rights