Highlights

A company's claim for proposal preparation costs was based on decisions that a contract award was improper. The claim was denied because it was not reasonably certain that the claimant would have received the award, if not for improper agency action, since its price exceeded the statutory cost limitation, and it was difficult to predict what technical or price changes other offerors would have made.