Issue Involving Correction of Bid Before Court of Competent Jurisdiction
B-191112
Feb 22, 1978
Skip to Highlights
Highlights
A company requested review of bid corrections on a construction contract awarded by an Environmental Protection Agency grantee. The company previously protested against the award and then filed a suit in U.S. District Court. Since the matter is before a court, GAO will not review.
Downloads
GAO Contacts
Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel