Protest to award of a contract was based on contention that evaluation criteria in the RFP were not properly applied, that the criteria were changed without notice to the offerors, and that price evaluation improperly excluded certain costs. In addition, protester questioned determination that the technical proposals were essentially equal. Agency determination that technical proposals were equal was not subject to objection. Cost may become determinative when proposals are equal technically. Transition costs were properly not considered. The protest was denied. (QM)