Bid Was Subject to More Than One Interpretation
B-187477
Mar 15, 1977
Skip to Highlights
Highlights
A claimant protested the rejection of its bid for valves as nonresponsive and the subsequent award of the contract to another bidder. The bid language was subject to more than one interpretation, one of which was nonresponsive; the bid rejection was proper.