Request for Relief Based on Alleged Mistake in Bid

B-187672 Nov 16, 1976
Jump To:
Skip to Highlights

Highlights

Modification of a contract was requested, based on an alleged unilateral mistake in bid. After contract award, the company notified the contracting officer that it had inadvertently omitted freight charges from its bids for items 2 and 3. Relief may not be granted from the valid and binding contract.