Procuring Bid Rejected Because of Company Quotation Stating Delivery Would Be 60 Days after Receipt of Written Contract

B-187614 Nov 09, 1976
Jump To:
Skip to Highlights

Highlights

Company protested the rejection of its low bid as nonresponsive because bid specifications required delivery 60 days after date of contract, not receipt of contract. Protest was denied. (SS)