B-187026 Nov 03, 1976
Jump To:
Skip to Highlights

Highlights

A protest which concedes that the low bidder convincingly established the existence of a mistake in the bid and of the bid actually intended, but contends that the contracting officer should be "estopped" from permitting the correction because this exercise of his discretion conflicted with alleged unwritten agency policy, is denied because elements of equitable estoppel have not been shown to exist.