Protest Against Rejection of Low Bid as Nonresponsive
B-185097
Published: Jan 23, 1976. Publicly Released: Jan 23, 1976.
Skip to Highlights
Highlights
The protester objected to the rejection of its low bid as nonresponsive, contending that bids were not required to be submitted on the standard form. The bid, which was submitted in the form of a letter rather than on the solicitation's standard form, was properly rejected as nonresponsive since the letter stated that the bid was subject to conditions which varied in several material respects from the terms and conditions of the solicitation.