Skip to main content

Claim for Expenses Incurred in Proposed Project for Reconstruction of Suez Canal

B-183247 Jan 27, 1976
Jump To:
Skip to Highlights

Highlights

A company requested reconsideration of the disallowance of its claim for expenses incurred in connection with a proposed project for reconstruction of the Suez Canal. Evidence furnished by the State Department indicated that the proposed project resulted from a routine suggestion that a proposal should be submitted to the Egyptians and that the company was a volunteer not entitled to compensation for expenses incurred in developing the project.

Downloads