Protest Against Rejection of Bid as Nonresponsive for Failure To Include Affirmative Action Certification
B-184582
Published: Jan 28, 1976. Publicly Released: Jan 28, 1976.
Skip to Highlights
Highlights
The protester objected to the rejection of its bid as nonresponsive. The bid was properly rejected as nonresponsive since the portions of the invitation containing the affirmative action requirements and certification were not submitted with the bid at bid opening. Information submitted after bid opening was not for consideration in determining the responsiveness of the bid.