Request for Reformation of Contract With Sevier County, Arkansas
B-185901
Published: Apr 14, 1976. Publicly Released: Apr 14, 1976.
Skip to Highlights
Highlights
A decision was requested on the proposed reopening and reformation of a completed contract because of a mutual mistake concerning road design and the agency's unilateral error in furnishing defective specifications. Although completion of performance bars a contractor's subsequent allegation of mistake in a contract, there is no objection to reopening and modification of the contract to provide road repair relief.