Protest Involving Ambiguous Bid
B-186623
Published: Jul 22, 1976. Publicly Released: Jul 22, 1976.
Skip to Highlights
Highlights
A company protested a proposed award and challenged the validity of a mistake in bid determination. The bid must be rejected as ambiguous because the total of subitems exceeded the bid for that item. The aggregate bid was not low based on the actual total, and the bidder cannot elect the price to be considered.