Protest Against Cancellation of Step II of Two-Step Procurement
B-185191
Published: Nov 20, 1975. Publicly Released: Nov 20, 1975.
Skip to Highlights
Highlights
A company protested the cancellation of step II of a procurement and the subsequent sole-source negotiations, maintaining that it could provide the equipment desired by the agency and requesting the opportunity to compete. The awardee was the only acceptable offerer in step I, and negotiation of a sole-source contract with the only acceptable offerer was reasonable.