Skip to main content

Protest Alleging Failure of Agency To Obtain Adequate Competition

B-184241 Published: Dec 09, 1975. Publicly Released: Dec 09, 1975.
Jump To:
Skip to Highlights

Highlights

The protester objected to the proposed award of a contract, alleging that the agency neither sought nor accepted adequate competition. The decision to award the contract for technical services to the only source the agency considered qualified was justified since it was essential to have continuity of work assignments by the only firm with a high degree of expertise in order to facilitate a quick response in a highly specialized area of work, and other firms could not demonstrate sufficient technical qualifications to do the work.

Full Report

Office of Public Affairs