Skip to main content

Protests Against Contract Awarded by Grantee

B-183497 Published: Aug 11, 1975. Publicly Released: Aug 11, 1975.
Jump To:
Skip to Highlights

Highlights

The protesters objected to the rejection of offers as nonresponsive and the award of a contract to another bidder under a grant. The protests were considered because the courts in which the matter was being litigated expressed an interest in GAO views. Rejection of the low bid under a grantee's solicitation as nonresponsive was not proper since the basis for determining responsiveness was not stated in the solicitation. The contract should be terminated and awarded to the low bidder.

Full Report

Office of Public Affairs