Protest Alleging Improper Bid Preparation

B-182978 Published: Jun 09, 1975. Publicly Released: Jun 09, 1975.
Jump To:
Skip to Highlights

Highlights

A protester against a contract award contended that the awardee did not prove that the officer who signed the bid had authority to do so and failed to initial changes in the price column. Proof that the signer of a bid has authority to bind the bidder may be provided after bid opening, and failure to initial the changes was not proven and, in any event, may be waived as a minor informality.