B-307137, Department of Energy--December 2004 Agreement with the United States Enrichment Corporation, July 12, 2006
The Honorable Pete V.
Domenici
Chairman, Committee on Energy
and Natural Resources
United States Senate
Subject: Department
of Energy—December 2004 Agreement with the United
States Enrichment Corporation
Dear Mr. Chairman:
This responds to the Committee’s request for a legal opinion regarding what has
been referred to as a “barter arrangement” between the Department of Energy
(DOE) and the United States Enrichment Corporation (USEC) under a
As discussed below, on the first issue, we conclude that DOE was authorized to
enter into the December 2004 Agreement by section 3112(b)(2)(D) of the USEC
Privatization Act of 1996, 42 U.S.C. sect. 2297h-10(b)(2)(D). As required by that provision, DOE sold and
received payment for Russian-origin uranium to be consumed by domestic end
users, and DOE’s failure to act within statutory deadlines did not terminate
its authority. On the second issue, we
conclude that DOE’s actions violated the requirements of 31 U.S.C. sect. 3302(b), the miscellaneous receipts
statute. When DOE directed USEC to receive, retain, and use proceeds from the sale of
government-owned uranium to compensate USEC for expenses it incurred on behalf
BACKGROUND
The Energy Policy Act of 1992 created USEC as a wholly owned government
corporation to perform all uranium enrichment services for commercial purposes
in the
In early 2001, USEC notified DOE that up to 9,550 MTU that DOE had
transferred to it was potentially contaminated with technetium[6]
and claimed that DOE was liable for damages arising from this transfer.[7] To resolve its claim, USEC asked DOE to
replace USEC’s contaminated uranium with uncontaminated, or “clean,” uranium.
In the June 2002 Agreement, DOE compensated USEC for decontaminating
some of the uranium by taking title to and assuming responsibility for some of
USEC’s stockpile of depleted uranium waste, which would reduce USEC’s eventual
disposal costs.[11] In a 2004 Work Authorization, DOE compensated
USEC for decontaminating additional transferred uranium by paying an estimated
$31 million from DOE’s appropriations.[12] In an October 2004 Agreement, DOE agreed to
exchange clean DOE-owned uranium for contaminated USEC uranium.[13]
Finally, in December 2004, DOE and
USEC entered into the agreement at issue here, Memorandum of Agreement for the Continued Operation of the Portsmouth
S&T Facilities for the Processing of Affected Inventory in Fiscal Year 2005
and Thereafter, Dec. 10, 2004 (December 2004 Agreement). Like most of the previous agreements, the
December 2004 Agreement specified that USEC would decontaminate the contaminated
uranium transferred to it by DOE and that USEC
would release DOE from liability for the previous contaminated transfers.
The clean uranium that DOE agreed to transfer to USEC was deemed Russian-origin
uranium under section 3112(b)(1) of the USEC Privatization Act. December 2004 Agreement, sect. 4.2, at 7. The Agreement also acknowledged that if the
transferred uranium were sold for consumption by domestic end users, it would
be subject the use restrictions in section 3112(b)(2)(D) of the act.
Twelve days after DOE signed the
December 2004 Agreement, it approved USEC’s marketing strategy for sale of 900
MTU of DOE clean uranium. In its
approval memorandum, DOE stated that the December 2004 Agreement “has in effect
made USEC the department’s sales agent for” the uranium.[14] From December 2004 to November 2005, DOE transferred about 900 MTU to USEC under
the Agreement, and USEC sold this uranium to four buyers for a total of $62
million for eventual consumption by domestic end users. GAO-06-723, at 18.
In November 2005, in section 314 of DOE’s appropriations act for fiscal year
2006, Congress expressly authorized DOE, notwithstanding any other provision of
law, including section 3112 of the USEC Privatization Act and the miscellaneous
receipts statute, 31 U.S.C. sect. 3302(b), “to barter, transfer or sell
uranium . . . and to use any proceeds . . . to remediate uranium inventories”
held by DOE. Energy and Water
Development Appropriations Act, 2006, Pub. L. No. 109-103,
sect. 314, 119 Stat. 2247, 2281 (
ANALYSIS
Agreement
DOE relies on section 3112(b)(2)(D) of the USEC Privatization Act as authority
for the December 2004 Agreement. In
support of its position, DOE provided us with a draft memorandum entitled Sales of Uranium Hexafluoride Pursuant to
Section 3112(b) of the United States Enrichment Corporation Privatization Act,
42 U.S.C. 2297h-10, dated “4/18/03 + 4/24/03” (2003 DOE Memo), addressing
DOE’s authority under section 3112(b)(2)(D). DOE told us that this 2003 memorandum
represents the department’s current legal position on its authority for the
December 2004 Agreement. Telephone Conference
Call with Mary H. Egger, Deputy General Counsel, and Susan F. Beard, Assistant
General Counsel, DOE, and Susan D. Sawtelle, Associate General Counsel, GAO,
and others, May 5, 2006. See also 2006 DOE Letter, Attachment at
2–3.[15]
Section 3112(b)(2) authorizes DOE sales of Russian-origin uranium and provides
that DOE “shall sell, and receive payment for” this category of uranium within 7 years
of enactment, that is, no later than
DOE maintains that its transfer of
uranium to USEC under the December 2004 Agreement constituted the requisite “sale” under section 3112(b)(2)(D), and that USEC’s release of its liability
claims against DOE, together with its decontamination of DOE’s uranium,
constituted the requisite “payment.”
2006 DOE Letter, Attachment at 6; 2003 DOE Memo, at 7–9.
We agree that DOE ultimately sold and received payment for the uranium, but not
that it was a sale to USEC. Instead, the
December 2004 Agreement established USEC as DOE’s sales agent for sales of the
uranium to other entities. The extent of
control that DOE retained over the uranium it transferred to USEC under the
Agreement does not support DOE’s characterization of the transfer as a sale to
USEC.
While the Agreement provided that DOE would “transfer to USEC title to
and possession of” clean uranium belonging to the United States, December 2004
Agreement, sect. 2.2, at 7, USEC had no discretion over use of the
uranium. The Agreement required that
USEC sell the uranium on terms and conditions detailed in a DOE-approved marketing
strategy using “its good faith efforts to obtain the best possible price given
market conditions at the time of the sale.”
The December 2004 Agreement also restricted the uses to which USEC
could apply the sale proceeds—they could be used only to compensate USEC for allowable
costs. December 2004 Agreement, sect. 6.2,
at 8. “Allowable costs” were defined as
the “direct, indirect, and plant overhead costs” that USEC incurred in
operating its facilities for processing “Affected Inventory,” which included both
USEC-owned and DOE-owned contaminated uranium.
We cannot reconcile these contract terms and practices with DOE’s assertion
that it sold the uranium to USEC. USEC
had no choice in whether to sell the uranium, or in how to go about it. The agreement required sale and required DOE to
approve the marketing plan. The
relationship between the two parties was more like a principal-agent
relationship. The principal instructed
the agent, USEC, in the sale, the placement of proceeds in a separate account,
the allowable uses of proceeds, and allowable costs. We find it far more reasonable to conclude
that the December 2004 Agreement accomplished not the sale of uranium to USEC,
but rather the designation of USEC as DOE’s sales and marketing agent. DOE itself, 12 days after signing the
December 2004 Agreement, identified USEC as DOE’s sales agent for the uranium
transferred pursuant to the Agreement, not the purchaser of the uranium. See Gunter
Memorandum.
As the
While the December
2004 Agreement obligated DOE to transfer “title to and possession of” the
uranium to USEC, the terms of the Agreement together with its collateral
security agreement demonstrate that the purpose of the transfer actually was to
facilitate the sale of the uranium to other commercial entities by USEC on
behalf of DOE. It is common for selling
agents to be given title and possession to property in order to effect a sale
on behalf of the principal. Restatement
(Second) of Agency sect. 14N (1958) (independent contractor agents “also fall within the category of trustees, as in the case of
a selling agent who has been given title to the subject matter . . . [and]
there is an agency [relationship] if in the transaction which they undertake
they act for the benefit of another and subject to his control”). The terms of the December 2004 Agreement and
the security agreement show that DOE retained control over the use and
disposition of both the uranium and the proceeds from its sale. Despite the recitation in the December 2004
Agreement transferring title and possession to USEC, the security interests
that DOE retained in its security agreement served to protect DOE’s title to
the uranium and the sales proceeds. DOE actually
parted with no incidents of ownership.
Between December
2004 and November 2005 (when Congress passed section 314), USEC sold the
uranium to four different buyers for a total of $62 million. GAO-06-723, at 18. USEC, acting as DOE’s sales agent, received
payment from the four buyers on behalf of DOE.
While we disagree with DOE’s assertion that it sold the uranium to USEC,
we conclude that DOE, using USEC as its agent, sold the uranium and received
payment, satisfying the requirements of section 3112(b)(2)(D).
B. DOE’s Failure
to Meet Statutory Deadlines
As noted above, section 3112(b)(2) provided that DOE “shall” sell and receive
payment for its Russian-origin uranium no later than April 26, 2003, and
section 3112(b)(2)(D) provided that sale of this uranium for consumption by
domestic end users “shall” occur in calendar year 2001. Thus, the next issue is whether DOE’s
authority under section 3112(b) had expired before it entered into the December
2004 Agreement. Although arguably the
word “shall” in these provisions could be construed as a mandatory command that
terminated DOE’s authority when it missed the deadlines, rendering the December
2004 Agreement unauthorized under that section,[17]
DOE asserts that the deadlines were only hortatory and did not affect its
authority. Conference Calls of May 8 and
9.
DOE relies on Barnhart v. Peabody Coal Co., 537 U.S.
149 (2003), and related cases. See
2003 DOE Memo, at 5–6. Barnhart involved a requirement under
the Coal Industry Retiree Health Benefit Act of 1992 (Coal Act) that the Social
Security Administration (SSA) “shall, before
The Supreme Court ruled in Barnhart
that SSA’s authority to make assignments did not expire on
Based on the absence of an explicit statutory consequence for noncompliance
with the deadlines and the lack of intent to terminate SSA’s authority in the
structure, purpose, or legislative history of the Coal Act, the Court held that
SSA’s authority was not time-limited. The fact that the deadline was located within
the same subsection as the Commissioner’s authority to act did not indicate the
agency’s authority was co-terminous with the deadline. The Court rejected this as a formalistic rule
that would “thwart the statute’s object” of having private companies pay for
most of the retiree benefits, because under the fallback provision that
allegedly applied if SSA’s authority were read as time-limited, benefits would
largely be paid by the public. Barnhart, 537
As in Barnhart, section 3112(b)(2) of the USEC
Privatization Act provided that DOE “shall” sell its Russian-origin uranium by
2001 or 2003, but specified no consequence for failure to do so. As DOE notes, the statute did not condition
the department’s authority by use of terms such as “unless” or “until.” 2003 DOE Memo at 6. Thus under Barnhart, the deadlines in section 3112(b) are to be read as
targets rather than jurisdictional mandates unless the Privatization Act’s
structure, purpose, or history reveals a contrary legislative intent.
We find no such contrary intent. Section
3112 contains a non-time-limited provision authorizing DOE sale and
transfer of uranium at any time—section 3112(d)—which arguably indicates that
DOE’s section 3112(b) authority was time-limited. Under this argument, even if DOE missed the
deadlines in section 3112(b), it could still sell its Russian-origin uranium
under the fallback provision of section 3112(d). However, we agree with DOE that as in Barnhart, there is no indication that
Congress intended section 3112(d) as a fallback to section 3112(b).[18]
Section 3112, entitled “Uranium transfers and sales,” directs DOE how to carry
out virtually every step of the disposition of both Russian-origin
and other uranium in DOE’s inventory—from the allowable timing of sales and
transfers, to the permissible recipients and uses, to the maximum volumes, and
even to end user consumption rates—with different sections governing different
categories of uranium. Section 3112(b)
specifically authorizes DOE to sell Russian-origin uranium, setting detailed
timetables and quantity limits on the sale of this category of uranium. Section 3112(d), by comparison, authorizes
DOE’s sale and transfer of uranium from its “stockpile” (an undefined term) at
any time subject to certain conditions.
Under the basic tenet of statutory construction that the more specific
statute takes precedence, see, e.g.,
Preiser v. Rodriguez, 411
The legislative history of the USEC Privatization Act lends further support to
the interpretation that section 3112(d) was not intended as a fallback to
section 3112(b). Congress believed that
one of the biggest impediments to privatizing USEC was investor concern about
the potential adverse impacts of an agreement known as the Russian HEU
Agreement.[19] The concern was that under this agreement,
inexpensive Russian-origin uranium would flood the U.S. market, depressing
prices for domestic uranium producers, threatening job security for domestic
uranium enrichment industry workers, and making USEC’s enrichment and marketing
services less competitive.[20] Congress therefore carved out section 3112(b)
as a separate, specific authority for sale of Russian-origin uranium, imposing
restrictions on its sale to minimize adverse impacts on the domestic market,
while still meeting
The same legislative
history indicates that Congress intended the section 3112(b) deadlines “as a
spur to . . . action, not as a bar to
tardy completion” of DOE’s obligation to sell Russian-origin uranium. Barnhart,
537
II. DOE’s Authority to Use Proceeds from
USEC’s Sales of the Uranium
The second issue is whether DOE
had authority to use the proceeds of USEC’s sale of DOE uranium pursuant to the
December 2004 Agreement. Under the
miscellaneous receipts statute, 31 U.S.C. sect. 3302(b), “an official or agent of
the Government receiving money for the Government from any source shall deposit
the money in the Treasury as soon as practicable without deduction for any
charge or claim.” 31 U.S.C.
sect. 3302(b). See, e.g., B-302825,
As noted above, DOE
asserts that with the December 2004 Agreement, the Department sold uranium to
USEC but not for cash. Conference Calls
of May 8 and 9; 2006 DOE Letter,
Attachment at 1. DOE officials conceded
that at the time of the Agreement, the department had no authority to retain
proceeds from its sales of uranium, and that if USEC had paid cash for the
uranium, DOE would have been required to deposit the proceeds into the
miscellaneous receipts of the Treasury. Conference
Calls of May 8 and 9. According to DOE officials,
USEC, instead of paying cash in consideration for DOE’s sale of uranium, agreed
to (1) release any claims of liability for the decontaminated uranium that DOE had
transferred to USEC under previous agreements, and (2) decontaminate DOE-owned
uranium.
As discussed
above, the terms of the December
2004 Agreement, as well as DOE’s actions in implementing the Agreement, do not
support the department’s characterization of the transfer of uranium as a sale
to USEC. DOE itself characterized USEC
as its sales agent, not its buyer. Gunter
Memorandum. By transferring uranium to
USEC for sale and permitting USEC to use sales proceeds to defray its costs of
decontaminating the uranium that DOE had transferred to it pursuant to earlier
agreements, DOE received from USEC a release from any claims of liability that
USEC might have against the department for transferring contaminated
uranium. We, of course, have no
objection to DOE transferring clean uranium to resolve its dispute with USEC. Public policy dictates in favor of the
government addressing its disputes. 71
Comp. Gen. 340, 341 (1992). See also Cannon Construction Co., Inc. v.
United States, 319 F.2d 173, 178–79 (Ct. Cl. 1963); B‑306860,
Feb. 28, 2006 (OFHEO could use an enforcement settlement agreement to
require regulated entity to format electronic documents to enable OFHEO to
pursue charges against the entity’s former officers); B‑237742, Mar. 14, 1990 (Army may use settlement agreements
to resolve claims by contractors). A
transfer of uranium in these circumstances and for this purpose would relate
back to the original transfers (between 1993 and 1998) and, like those
transfers, is authorized by the Privatization Act. See
42 U.S.C. sect. 2297h-2(b).
That, however, is not
what happened here. With the December
2004 Agreement, DOE initiated a stream of revenue (the sales proceeds) that DOE
used to cover the costs of decontaminating both the USEC-owned and DOE-owned
contaminated uranium. This is
problematic. It
is well understood that in the absence of statutory
authority, “what cannot be done directly cannot be done indirectly.” E.g., B‑303927,
In similar circumstances both GAO and the courts have recognized that a
contractor constructively receiving money for an agency is not free of the
requirement of the miscellaneous receipts statute that funds received for the
use of the United States be deposited in the Treasury just as if they had been
received directly by the agency. See, e.g., Scheduled Airlines Traffic
Offices, Inc. v. Department of Defense, 87 F.3d 1356, 1361–63 (D.C. Cir.
1996) (Defense
Department cannot require payment to morale fund of a portion of concession
fees derived from unofficial travel); Motor Coach Industries, Inc. v.
Dole, 725 F.2d 958, 968 (4th Cir. 1984) (Federal Aviation
Administration (FAA) cannot hold in a trust fund amounts paid by airlines to
defray FAA’s cost of acquiring new shuttle buses for Dulles Airport); B-300826, Mar. 3, 2005 (National
Institutes of Health (NIH) could not authorize its contractor to charge a fee
to cover the costs of a formal conference that NIH hosted); B-265727, July 19, 1996 (Securities and Exchange Commission may not reduce its
obligation of appropriated funds resulting from a lease, and correspondingly
increase its available appropriations, by subleasing space and arranging for
the sublessee to make its payments directly to the landlord).
DOE clearly had
authority to decontaminate its own contaminated uranium using funds
appropriated for that purpose. At the
time of the December 2004 Agreement, if DOE itself had sold its clean uranium,
rather than transferring the uranium to USEC to carry out the same task, the department
admits that it could not have legally retained the sales proceeds and applied
them to pay its decontamination costs. Instead,
DOE would have been required to deposit the sales proceeds into the miscellaneous
receipts of the Treasury and to use DOE’s appropriations to acquire
decontamination services. With the
December 2004 Agreement, DOE circumvented the miscellaneous receipts statute by
its use of USEC as its sales agent and its direct control of the disposition of
the sales proceeds. See B-287738, May 16, 2002 (because Maritime Administration
had effective control of the disposition of amounts held in an escrow account,
it had constructively received those amounts within the plain meaning of the
miscellaneous receipts statute).
DOE’s acquisition of decontamination services for its own uranium is conceptually indistinguishable from
a Small Business Administration (SBA) contract that we addressed in 2004,
B-300248, Jan. 15, 2004. In that case, SBA retained a contractor to help it perform regulatory
reviews of lenders participating in its Preferred Lenders Program (PLP). SBA arranged to compensate its contractor by
imposing fees on the PLP lenders and requiring the lenders to pay those fees
directly to the contractor. SBA had no
authority to retain and use those fees itself, nor could it allow its agent to
do so. 31 U.S.C. sect. 3302(a) and (b)
(“an official or agent of the United States Government . . . shall keep the
money safe without . . . using it [and] shall deposit the money in the Treasury
as soon as practicable without deduction for any charge or claim”). We observed that an agency receives money
under the miscellaneous receipts statute if the receipts are to cover the
expenses of the government or pay government obligations, B-300248, citing B-205901,
Here, as in the SBA case, DOE arranged for an independent revenue
stream not appropriated to it by Congress; had no authority to retain the
proceeds of that revenue stream if received directly; and arranged for its
agent, USEC, to receive the proceeds of the unauthorized revenue stream and to
use those amounts to pay for expenses incurred on behalf of DOE. In our view, DOE’s agent received “money for the
government” but failed to deposit the money in the Treasury, and therefore, DOE
violated the miscellaneous receipts statute and augmented its appropriations.
In defense of this
aspect of the December 2004 Agreement, DOE points to a 1988 decision of this
Office, 67 Comp. Gen. 510 (1988). See
2006 DOE Letter, Attachment at 6.
The 1988 decision and other decisions in that line address in-kind
replacement or repair of damaged government property, in lieu of a cash
payment, by a tortfeasor. In the 1988
case, the Bureau of Alcohol, Tobacco and Firearms (ATF) asked if it could
accept a replacement vehicle from a negligent third party, who had damaged an
ATF vehicle beyond repair, without violating the miscellaneous receipts
statute. We concluded that ATF could
accept the replacement vehicle, “despite the fact that, had the tortfeasor paid
the government . . ., the money would have to be deposited as miscellaneous
receipts.” 67 Comp. Gen. at 511.
The 1988 decision
and related decisions have no application here.
These decisions address damage to government property resulting from
tortious acts, clearly not the factual situation present here. The purpose of the ATF and related decisions
is to facilitate the government, which has suffered damage, being made
whole. To require an agency to insist on
cash payable to the miscellaneous receipts account of the Treasury rather than
replacement or repair would not serve the public interest. Again, that is not the situation here. The purpose of the December 2004 Agreement
was not to remedy a tortious act against government property, but to settle
claims, to acquire decontamination of DOE-owned uranium, and to identify a
source of funds to pay for that service.[24]
As noted above, in
November 2005, Congress enacted in DOE’s appropriations for fiscal year 2006 a
provision that expressly authorizes
the department to “barter, transfer or sell uranium . . . and to use any
proceeds, without fiscal year limitation, to remediate uranium inventories”
held by DOE, notwithstanding any other provision of federal law, including
section 3112 of the USEC Privatization Act and the miscellaneous receipts
statute. Pub. L. No. 109-103,
sect. 314. Thus, at least for fiscal year 2006, section
314 permits DOE, through an agent like USEC, to sell government-owned uranium
and to use the proceeds to compensate USEC for decontaminating DOE’s
uranium.
We are aware that
USEC is the only American vendor currently offering domestic commercial uranium
enrichment services, and that all of the agreements DOE negotiated to address
USEC’s claims have included language reflecting the department’s desire that
USEC continue as a viable entity. Our
objection here is with DOE’s improper augmentation of its appropriations.
Because DOE’s
fiscal year 2005 “Departmental Administration” appropriation was available for
the purpose of decontaminating its uranium,[25]
to remedy its violation of the miscellaneous receipts statute, DOE should adjust
its accounts by transferring $62 million from this appropriation to the
miscellaneous receipts of the Treasury.[26] If DOE finds that it lacks sufficient budget
authority to cover the adjustment, it should report a violation of the
Antideficiency Act in accordance with 31 U.S.C. sect. 1351. In the alternative, DOE may wish to seek and
obtain congressional ratification of its use of the $62 million.
CONCLUSION
DOE was authorized under section 3112(b)(2)(D) of the USEC
Privatization Act to transfer uranium to USEC
under the December 2004 Agreement, as an interim step in USEC’s sale of such
uranium, on the department’s behalf, for consumption by domestic end
users. However, prior to the enactment
of section 314 of DOE’s fiscal year 2006 appropriations act, the department
used uranium sales proceeds (and earnings on those proceeds) in violation of
the miscellaneous receipts statute, 31 U.S.C. sect. 3302(b), which resulted in
DOE unlawfully augmenting its appropriations.
To resolve its improper use of the sales proceeds, DOE should either
seek and obtain congressional ratification of its use of the proceeds or adjust
its accounts.
If there are questions concerning these matters, please contact Susan
A. Poling, Managing Associate General Counsel, at (202) 512-2667, or Susan D.
Sawtelle,
Sincerely yours,
Gary L.
Kepplinger
General Counsel
B-307137
DIGESTS
1. Section 3112(b) of the USEC Privatization Act
of 1996, Pub. L. No. 104‑134,
110 Stat. 1321-335, 1321-344 (Apr. 26, 1996), 42 U.S.C. sect. 2297h-10(b), authorized the Department of Energy (DOE) to
transfer to the United States Enrichment Corporation (USEC) Russian-origin
uranium so that USEC could sell the uranium on DOE’s behalf for consumption by
domestic end users, as provided for in a December 2004 agreement between DOE and
USEC.
2. DOE violated
31 U.S.C. sect. 3302(b), the miscellaneous receipts statute, and augmented its
appropriations when it authorized USEC to hold, invest, and use the proceeds
from public sales of government-owned uranium to compensate USEC for costs it
incurred in decontaminating uranium on behalf of DOE, prior to enactment in
November 2005 of specific statutory authority exempting the proceeds of those
uranium sales from the miscellaneous receipts statute.
[1] On June 16, 2006, GAO reported to the Committee
concerning our review of certain management issues regarding this Agreement in U.S. Enrichment Corporation Privatization: USEC’s Delays in Providing Data Hinder DOE’s
Oversight of the Uranium Decontamination Agreement, GAO-06-723 (Washington,
D.C.: June 16, 2006).
[2] The
Antideficiency Act prohibits making or authorizing expenditures or obligations
that exceed available budget authority.
31 U.S.C. sect. 1341.
[3] Consistent with our regular practice, we
requested DOE’s legal views on these issues.
Letter from Susan A. Poling, Managing Associate General Counsel, GAO, to
David R. Hill, General Counsel, DOE, Feb. 9, 2006. On
[4] See Energy Policy Act of 1992, Pub. L. No. 102-486, title IX, sect. 901, 106 Stat.
2776, 2924 (
[5] See USEC
Privatization Act of 1996, Pub. L. No. 104-134, sections 3103–3106, 110 Stat.
1321-335, 1321-336 to -338, 42 U.S.C. sections 2297h-1 to
2297h-4; GAO-06-723, at 2.
[6] Technetium is a radioactive metal created as a
by-product of nuclear fission.
Commercial specifications for nuclear fuel severely limit the amount of
technetium that may be contained in uranium fuel, and the contamination
discovered by USEC exceeded those limits.
GAO-06-723, at 9.
[7] Memorandum from Dennis J. Scott, Assistant General
Counsel, USEC, to Matt Urie, Attorney-Advisor, DOE, Contaminated Uranium Inventory,
[8] See, e.g., Agreement
between the U.S. Department of Energy and USEC, Inc.,
[9] See, e.g., June
2002 Agreement pt. A, para. (a), at 12; Letter
Work Authorization,
[10] See, e.g.,
June 2002 Agreement art. 2, at 1, and art. 3, at 7.
[11] June 2002 Agreement pt. B, at 12.
[12] 2004 Work Authorization, sect. 4.1, at 5.
[13] October 2004 Agreement, sections 1.3, 1.4, at 3.
[14] Memorandum from Linda L. Gunter, Associate Director,
Office of Nuclear Fuel Supply Security, DOE, to William E. Murphy, Manager,
Portsmouth Paducah Project Office, DOE, Approval
of USEC’s Marketing Strategy For the Sale of 900 Metric Tons of Uranium (MTU)
in Response to Article 4 of the Memorandum of Agreement for Continued Operation
of the Shipping and Transfer facilities in FY 2005 and beyond, Dec. 22,
2004 (Gunter Memorandum).
[15] DOE also asserts that certain general authorities
under the Atomic Energy Act are “in harmony with the results achieved from” the
December 2004 Agreement or “likely also would have” or “might well” have
authorized the Agreement. See 2006
DOE Letter, Attachment at 1–3, citing
Atomic Energy Act sections 3(d), 63, 66, 161(g), 42 U.S.C. sections 2013(d), 2093,
2096, 2201(g). See also Memorandum for David K. Garman, DOE Acting Under Secretary
for Energy, Science and Environment, from Paul M. Golan, DOE Acting Assistant
Secretary for Environmental Management, Action:
Approve the transfer of programmatic
responsibility to the Office of Environmental Management for implementation of
a barter agreement with USEC for Continued Operation of the Portsmouth Shipping
and Transfer (S&T) Facilities to Process USEC and DOE contaminated
inventories of uranium hexafluoride (UF6) (Sept. 30, 2004) (citing same
authorities). Because we find that the December 2004 Agreement was
[16] USEC agreed to “waive any claim for fees”
for these decontamination services. December
2004 Agreement, at 2. Instead, USEC was entitled to credit the
“allowable direct, indirect, and plant overhead costs incurred” in
decontaminating the uranium against the revenues derived from the uranium sales.
[17] Perhaps the most fundamental principle of statutory
construction is that words in a statute must be given their ordinary or natural
meaning whenever possible. See Walters v. Metropolitan Educational
Enterprises, Inc., 519
[18] An interpretation that section 3112(d) applied as a
fallback where DOE missed the section 3112(b)(2) deadlines would render
the December 2004 Agreement unauthorized.
DOE staff told us that because the Department did not believe section
3112(d) applied, it took no action to meet the section 3112(d) sale conditions.
[19] See Agreement
Concerning the Disposition of Highly Enriched Uranium Extracted from Nuclear
Weapons, U.S.-R.F.,
[20] See, e.g., S.
Rep. No. 104-173, at 14 (1995) (“[T]he unrestricted entry into the market of
new, low cost feed materials could significantly disrupt uranium markets and
depress market prices.”); USEC
Privatization Act, Hearing on S. 755 Before the Senate Committee on Energy and
Natural Resources, S. Hrg. No. 104-105, at 2 (June 13, 1995) (remarks
of Chairman Murkowski) (“[W]e must . . . balance the interests of a very
important national nonproliferation initiative, the U.S.-Russian Highly
Enriched Uranium agreement. We must
maintain the chance of a free market for uranium enrichment. We must maintain the health of the uranium
mining industry, and we must ensure fairness to the workers of the enrichment
plants in
[21] It was precisely because DOE was concerned about an
already weak domestic market that it had not sold all of its Russian-origin
uranium by the April 2003 statutory deadline.
See 2003 DOE Memo, at 1–2. The same concern had prompted DOE to
recommend to Congress, in 2000 and 2002, that it remove or modify this
deadline. See DOE, Report to Congress on Maintenance of Viable
Domestic Uranium, Conversion and Enrichment Industries (December 2000), at
22; DOE, Report on the Effect [that LEU]
delivered under the Russian HEU Agreement has on the Domestic Uranium Mining,
Conversion, and Enrichment Industries, and the Operation of the Gaseous
Diffusion Plant (
[22] See, e.g., S.
Hrg. No. 104-105, at 17 (statement of USEC President William H. Timbers)
(“[S]ome have asked, ‘. . . [W]hy is this taking so long?’ . . . [T]his is a difficult, complex,
technically challenging program to implement.
This is not just a
[23]
Because
DOE’s position on its legal authority for the December 2004 Agreement has been
developed informally rather than through a formal rulemaking, adjudication, or
other rigorous process, it is not entitled to substantial deference under Chevron U.S.A. v. Natural Resources Defense Council,
467 U.S. 837, 842–45 (1984). See
[24] We also distinguish our recent decision,
B-306860,
[25] Consolidated Appropriations
Act, 2005, Pub. L. No. 108-447, 118 Stat. 2809, 2952 (
[26] Between
December 2004 and November 2005, USEC sold DOE’s uranium for a total of $62
million and used the proceeds to cover the costs of decontaminating USEC-owned
and DOE-owned uranium. GAO-06-723, at
18.

