B-402000, Building Restoration Corporation, December 29, 2009
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.
Decision
Matter of: Building Restoration Corporation
Timothy
A. Sullivan, Esq., and Jason C. Tarasek, Esq., Best & Flanagan LLP, for the
protester.
Capt. Bridget E. Keenan, Department of the Army, for the agency.
Cherie J. Owen, Esq., and Ralph O. White, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest that agency improperly
evaluated protester's proposal as marginal, and thus ineligible for award under
the terms of the solicitation, is denied where the record
shows that the agency reasonably concluded the proposal's deficiencies and weaknesses
warranted a technical rating of marginal, and thus properly made award to the lowest-priced, technically-acceptable offeror without conducting discussions.
DECISION
Building Restoration
Corporation (BRC) of Roseville, Minnesota, protests the award of a contract to
Hydro-Tech, Inc., of Lehi, Utah, under request for proposals (RFP)
No. W91QF4-09-R-0020, issued by the Department of the Army for repair of a
tower at Fort Leavenworth, Kansas. BRC contends that the Army's evaluation of its proposal was unreasonable.
BACKGROUND
The RFP was issued on July 14, 2009, and called for the
award of a fixed-price contract. The RFP
provided that award would be made, without discussions, to the lowest-priced,
technically-acceptable offeror. RFP at 10. Under the technical evaluation factor, the
RFP identified four subfactors: (1) prior experience with historic preservation
construction projects; (2) technical excellence; (3) management
capability; and (4) personnel qualifications.
Id.
To receive consideration for award, a rating of no less
than adequate was required for the first subfactor; ratings of no less than
acceptable were required for the remaining three subfactors. Id. at 10, 11, 17-18. As relevant here, the RFP stated that, with
regard to all of the subfactors except the first one, a rating of acceptable
would be assigned to proposals that contained some strengths, but no
deficiencies or significant weaknesses, provided any identified minor weaknesses did not impact the
probability of meeting minimum requirements.
A marginal rating would be assigned to proposals that contained numerous
weaknesses (including significant weaknesses) and/or some deficiencies, provided
the proposal's overall approach was sufficiently sound that the weaknesses or
deficiencies could be corrected without a major rewrite of the proposal. RFP at 18.
With
regard to the second subfactor, technical excellence, offerors were required to
describe the approaches they would use to ensure that the results of the
construction project met the specified requirements. Offerors were to prepare a summary plan for
elements necessary to complete the required work, including, but not limited
to, technical approaches and methods and means.
RFP at 15-16. As relevant here,
the RFP's specifications make numerous references to different types of
"Dutchman" repairs[1] to
be performed under the contract. See
AR, Tab 6, RFP Attach. 1, at 14, 18, 173-74, 177, 179, 181, 183, 185,
186-90. Further, the Dutchman work
comprised two separate lines on the schedule contained in the RFP. AR, Tab 6, RFP Attach. 1, at 14. The RFP also stated that the agency's
evaluation under the technical excellence subfactor would include an evaluation
of the offeror's construction schedule.
RFP at 11.
The
specifications also required offerors to provide a site safety and health officer
at the work site at all times to perform safety and occupational health
management, surveillance, inspections, and safety enforcement for the contractor. AR, Tab 6, RFP, Attach. 1, at 66. The specifications stated that the contractor
quality control person on this project could not also serve as the safety
officer. Id.
In
evaluating the protester's proposal, the technical evaluation board (TEB) assigned
a deficiency for the protester's construction schedule. AR, Tab 27, TEB Report, at 5. The TEB found that the schedule did not
appear to be thoroughly developed to demonstrate the sequence and overlap of
work required by solicitation specification sections 02 41 19, covering selective
demolition, and 04 01 20, covering the maintenance of masonry; the evaluators
also concluded that BRC's construction schedule was internally
inconsistent. AR, Tab 27, TEB Report, at
4; AR, Tab 29, Contracting Officer's (CO) Memorandum, at 15 (noting that BRC's
schedule contained an almost three-week delay between demolition of some
masonry and the replacement of that masonry).
The
TEB also noted that BRC's proposal did not identify a separate individual to
serve as the quality control person.
Instead, the proposal stated, "Our Safety Director also provides Quality
Control functions on his visits to job sites on a rotating basis. The Safety Director submits his reports
directly to management." AR, Tab 20, BRC
Proposal at 149. In its consensus
report, the TEB concluded that BRC's quality control program was insufficient
because, under the terms of the solicitation, the site safety officer could not
also serve as the quality control officer.
AR, Tab 27, TEB Report, at 5. The
TEB listed this as a deficiency under the technical excellence subfactor. Id.
The
board also noted that BRC's proposal failed to address the firm's experience making
Dutchman repairs. The board assigned a
weakness for this failure, concluding that the omission could mean that BRC
lacked such experience. AR, Tab 27, TEB Consensus
Report, at 4.
The
CO adopted these findings in her source selection decision. AR, Tab 29, CO Memorandum, at 14-15. The agency determined that BRC's technical
proposal was marginal, and therefore not eligible for award. Thus, the agency awarded the contract to Hydro-Tech,
Inc., at a price of $1,696,100.
On August
25, the agency provided BRC with a debriefing.
In the debriefing, the agency discussed the issues identified above, as
well as the other strengths and weaknesses assigned to BRC's proposal. AR, Tab 28, Debriefing Memorandum, at 5.
The protester filed an agency-level
protest on September 4. The agency
denied the protest on September 29, and this protest followed.
DISCUSSION
BRC contends that the agency's evaluation of its proposal was unreasonable, and that its proposal should have been evaluated as technically acceptable under all subfactors. Among other issues, BRC argues that the agency should not have assigned a deficiency to its proposal for its schedule. BRC also challenges the agency's assignment of a weakness for its failure to discuss Dutchman work in its proposal, arguing that this constitutes an evaluation criterion not set forth in the solicitation. As set forth below, we disagree with the specific contentions identified here, and with BRC's other challenges.[2]
Since, under the evaluation scheme here, a proposal had to
have an acceptable rating to be considered for award, and since a proposal with
deficiencies could not be rated acceptable, see RFP at 10-11, 17-18, we
consider first BRC's challenge to the agency's assessment of a deficiency with
regard to the firm's construction schedule.
Protest at 5. In this regard, BRC
disputes the agency's finding that the firm's construction schedule did not
reflect a full understanding of the potential problems of the project, was not
sufficiently developed, and contained inconsistencies. BRC also argues that the Army's conclusions
were unreasonable because the schedule committed to completing all required work
within the allotted time, and budgeted for an overlap of work to allow for
unforeseen conditions. Protest at 5,
Comments at 11.
The evaluation of technical proposals
is a matter within the discretion of the contracting agency. Marine
Animal Prods. Int'l, Inc., B‑247150.2, July 13, 1992, 92-2 CPD
para. 16 at 5. In reviewing an agency's evaluation, we will not reevaluate technical proposals;
instead, we will examine the agency's evaluation to
ensure that it was reasonable and consistent with the solicitation's stated evaluation criteria. MAR Inc.,
B‑246889, Apr. 14, 1992, 92‑1 CPD para. 367 at 4. An offeror's mere disagreement with the
agency's evaluation does not render the evaluation
unreasonable. McDonnell
Douglas Corp., B‑259694.2, B‑259694.3, June 16, 1995, 95‑2
CPD para. 51 at 18.
We have reviewed BRC's proposal and the agency's evaluation materials, and we see nothing unreasonable about the agency's conclusions. Specifically, we agree that, in evaluating an offeror's schedule, the agency was permitted to do more than merely ascertain whether the schedule committed to complete the project by the date specified in the solicitation. Instead, the agency reasonably reviewed the schedule and expressed concerns about its adequacy for ensuring that the project would be completed on time. In contrast, BRC has not--even in the course of its protest--explained how the agency's conclusions about weaknesses in BRC's schedule were erroneous, or unreasonable. Based on our review, we think the agency's assessment of a deficiency in this area was reasonable.
The protester also challenges several weaknesses assigned
to its proposal. For example, BRC argues
that the agency imposed an unannounced evaluation criterion with regard to its
failure to address Dutchman repairs, since the RFP did not list Dutchman work
as an evaluation factor. We disagree.
A solicitation must inform offerors of the basis
for proposal evaluation, and the evaluation must be based on the factors and
significant subfactors set forth in the solicitation. Federal Acquisition Regulation
(FAR) sect. 15.304(d); Akal Sec., Inc., B‑271385,
B-271385.3, July 10, 1996, 96-2 CPD para. 77 at 3.
Agencies are required to identify evaluation factors and significant
subfactors, but they are not required to identify all areas of each which might
be taken into account, provided that any unidentified areas are reasonably
related to or encompassed by the stated criteria. Smart Innovative Solutions,
B-400323.3, Nov. 19, 2008, 2008 CPD para. 220 at 4.
Here, we agree with the agency that an offeror's
experience with Dutchman repairs was reasonably encompassed under the technical
excellence subfactor. This subfactor
required that offerors describe the technical approaches and methodology
necessary to complete the required work.
In addition, as set forth above, Dutchman repairs were referenced
numerous times throughout the specifications, and were
specifically mentioned on the schedule contained in the RFP.
Moreover, we note for the record that there was an
additional deficiency identified in BRC's proposal that the protester did not
challenge in its protest filing at GAO; thus, even if the protester prevailed
on the challenges it raised--which it does not--it would remain ineligible for
award. Specifically, the TEB assigned a
deficiency for the firm's failure to follow the solicitation's express requirement
that the safety officer could not also serve as the quality control
officer. AR, Tab 27, TEB Consensus
Report, at 5. Not only did the CO adopt
this finding in her selection decision, AR, Tab 29, CO Memorandum, at 15, but
this deficiency was also noted in the debriefing memorandum. AR, Tab 28, Debriefing Memorandum, at 5. Although BRC challenged this finding in its
agency-level protest, AR, Tab 31, Agency-Level Protest, at 2, and although the
agency addressed it, AR, Tab 31, Decision on Agency-Level Protest, at 6, this
issue was not raised in BRC's protest to our office. Hence, on the basis of its nonconforming
proposal, BRC is ineligible for award under the terms of this solicitation.
We deny the protest.
Lynn H. Gibson
Acting General Counsel
[1] A Dutchman repair is defined in the specifications as the process of removing damaged stone to a specified depth and inserting a new piece of stone to fit in the opening created to form a seamless patch. AR, Tab 6, RFP Attach. 1, at 173. The specifications also reference and define a full-face Dutchman, a multi-face Dutchman, a Dutchman joint, and a Dutchman collar joint. Id. at 173-74.
[2] BRC
also challenges the agency's evaluation under the prior experience technical
subfactor on the basis that its rating of neutral was unreasonable. Protest at 3-4. However, because a rating of neutral does not
render a proposal ineligible for award under the evaluation scheme here, BRC
was not prejudiced by the rating.
Moreover, to the extent BRC claims the agency committed fraud and acted
in bad faith, see Protest at 6, we dismiss the protest. There is no evidence in the record, other
than BRC's speculation, to support the protester's attribution of unfair or
prejudicial motives to the agency's evaluation. Because government officials
are presumed to act in good faith, a protester's claim that contracting
officials were motivated by bias or bad faith must be
supported by convincing proof; we will not attribute unfair or prejudicial
motives to procurement officials on the basis of inference or supposition. Diversified Maint. Sys., Inc.,
B-401329.4, Nov. 9, 2009, 2009 CPD para. 226 at 4 n.7; Shinwha
Elecs., B-290603 et al., Sept. 3, 2002, 2002 CPD
para. 154 at 5 n.6. Moreover, as
discussed in this decision, we conclude the agency's evaluation of BRC's
proposal was reasonable.







