B-401793, M. Matt Durand, LLC, November 23, 2009
|
Matter of: M. Matt Durand, LLC
Mary
Elizabeth Hall, Esq., Mockbee Hall Drake & Hodge Law Firm, for the
protester.
Janis R. Millete, Esq., U.S. Army Corps of Engineers, for the agency.
Frank Maguire, Esq., and John M. Melody, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1.
Protest that, during discussions, agency permitted other offerors, but
not protester, to address issues regarding "borrow site" for earthen clay fill
material, and that discussions therefore were unequal, is denied where agency
was unaware of deficiency in protester's proposal with regard to borrow site at
time of discussions; consistent with solicitation, agency obtained information
regarding proposed borrow site issues subsequent to discussions.
2. Contracting
officer reasonably eliminated protester's proposal from competition where its
proposed earthen clay "borrow site" was determined to be unacceptable due to
failure to meet environmental requirements, and she had no reason to question
that determination.
DECISION
M. Matt Durand, LLC, of St.
Martinsville, Louisiana, protests the rejection of its proposal under request
for proposals (RFP) No. W912P8-08-R 0022, issued by the U.S. Army Corps of
Engineers for services and supplies related to delivery of earthen clay
material for improving the Greater New Orleans Area Hurricane and Storm Damage
Risk Reduction System. Durand principally
asserts that the Corps conducted unequal discussions and unreasonably
eliminated its proposal from the competitive range.
The RFP, issued on June 3, 2008, provided for award to the
offeror submitting the lowest priced, technically acceptable proposal. RFP at 143-46. Technical acceptability was to be determined
based on 13 subfactors. RFP at
143-146. Proposals found technically
acceptable would then be evaluated for price using a reverse auction
approach. Id. at 146.
The Corps was required by the National Environmental
Policy Act (NEPA), 42 U.S.C. sect. 4371 et seq., to complete an
environmental analysis of offerors' proposed earthen clay "borrow sites" (i.e.,
the areas from which the earthen clay material would be excavated). See 33 C.F.R. Part 230, Procedures for
Implementing NEPA. To satisfy this
requirement, the Corps utilized an Individual Environmental Report (IER), an
"alternative NEPA arrangement" authorized by the NEPA regulations. Id.
The RFP specifically made approval of an offeror's "material sources and
operations" in an IER a condition for continued participation in the reverse
auction and eligibility for award. RFP
at 145-46. The IER pertinent to the
acquisition here was IER 30, "Contractor-Furnished Borrow Material #5; St.
Bernard and St. James Parishes, Louisiana, and Hancock County
Mississippi." Agency Report (AR) Tab 29.
The Corps's environmental review under NEPA included a
review for compliance with section 106 of the National Historic Preservation
Act (NHPA), 16 U.S.C. sect. 470f, which is designed to
ensure that historic properties are considered during federal project planning
and execution. AR at 3.[1] Consistent with this requirement for
consideration of historic properties, the RFP required each offeror to include
with its proposal a Cultural Resources Impact Report (CRIR) prepared by a
professional cultural resource management company meeting the standards of
NHPA. RFP at 124. The acceptability of an offeror's CRIR was a
technical evaluation subfactor under the RFP, as well as a factor in determining
inclusion of an offeror's proposal under the IER. RFP at 144, 145-46.
In August 2008, 16 proposals were received, including
Durand's. Durand proposed the Port
Bienville borrow site in Mississippi as the source of the required earthen
clay. Contracting Officer's Statement
(COS) at 3. Durand's proposal included a
CRIR. Id. After the initial evaluation by the source
selection evaluation board (SSEB), 13 proposals, including Durand's, were
included in the competitive range. Id.
at 4. The SSEB found Durand's proposal
to have deficiencies with regard to three technical subfactors: geotechnical report, borrow area management
plan, and transportation and stockpiling plan.
No weaknesses or deficiencies were noted with regard to the other 10
subfactors, including the CRIR. The
competitive range offerors, including Durand, were advised of their proposals'
evaluated weaknesses and deficiencies.
Three offerors (not Durand) were advised of weaknesses and deficiencies
in their CRIRs. Id.
In February, 2009 the Corps received revised proposals
from 12 offerors (1 offeror did not submit a revised proposal). AR Tab 11.
On March 12, following evaluation of the revised proposals, seven
offerors, including Durand, were advised that their proposals had been
"determined technically acceptable" and would remain in the competitive
range. The notifications further
advised:
Your proposal will enter an alternative National Environmental Policy Act arrangement pursuant to the statutory requirements of 42 U.S.C. 4371, as disclosed in the solicitation. This process may take up to one hundred and twenty (120) days.
COS at 5; see, e.g., AR Tab 13, Agency
Letter to Durand, Mar. 12, 2009.
Consistent with the March 12 letter, the remaining
proposals, including Durand's, were subjected to the NEPA process described in
RFP sect. 5.1.1, above. As part of this
process, by letters dated June 1, the Corps's Environmental Planning and
Compliance Branch (EPCB) requested that various interested entities, including
Indian tribes and Mississippi State officials, comment on Durand's proposed
Port Bienville borrow site. AR Tab
16. These letters advised that the Corps
had determined that the Port Bienville site "does not contain significant
cultural resources," but included a copy of the CRIR prepared by Durand's
consultant and generally advised that the "undertaking has the potential to
affect historic properties." See,
e.g., id. at 1-2.
The EPCB received several responses to the June 1
letters. By letter dated June 8, the
Jena Band of Choctaw Indians advised the EPCB that it was "not in agreement"
that the Port Bienville site "should not be considered … a historic property"
under section 106. AR Tab 17. The Jena Choctaws also advised that the site
"may be of greater significance to the Choctaw people." Id.
By letter of June 25, the Mississippi State Historic Preservation
Officer (MSHPO) advised the EPCB that it had "no objections to the proposed
undertaking." AR Tab 18. However, in a second letter, dated June 29,
MSHPO advised EPCB that it had come to his attention "that there may be
significant Choctaw cultural resources in the project area, including the
possibility of burials," and went on to state that, "As such, we are
withdrawing our previous concurrence and will be in consultation with the
Mississippi Band of Choctaw Indians before providing any further comments on
this project." AR Tab 19. By e-mail dated June 30, the Mississippi Band
of Choctaw Indians advised that it had "a number of concerns with the project,"
including the "high probability" of "intact or disturbed human burials," and
that, "If there are human bones there, they must be recovered and treated in a
respectful manner, not bulldozed away or made fill for a levy." AR Tab 20.
The tribe further advised that "a 100% survey of the area needs to be
completed," and noted that the "archeological reports on this project do not
even mention that this Choctaw community existed, let alone address the
possible presence of house sites cemeteries, or burials." Id.
Finally, the tribe cautioned that "This obviously is of significant
concern to us and must be addressed before this project can move forward." Id.
By letter dated July 15, the EPCB advised Durand that it
had decided to deny the proposed Port Bienville site as a source of borrow
material for IER 30. AR Tab 22. The EPCB cited the objections of the Jena and
Mississippi Choctaws and the withdrawal of SHPO's concurrence in approval of
the site. Id. The letter further advised that "Resolution
of these issues may involve the completion and review of additional and
extensive cultural resources investigations at your expense." Id.
In a letter dated July 20, Durand responded to the EPCB's
July 15 letter, disputing several of the conclusions therein. AR Tab 24.
Durand asserted that there was no archeological site of concern within
the proposed excavation site, that the only site was "nearly a half-mile away,"
and that there thus would be "no adverse impact." Id.
Durand further advised that its consultant had met with the Mississippi
Choctaws' archaeologist in an effort to identify specific Choctaw concerns, and
that the Choctaw archaeologist indicated that the Choctaws' concerns were
settlements that were in the area as well as the potential for human remains
that may have been interred near residences.
Id. These settlements were
known to a Choctaw Elder living in the area and Durand's consultant was
scheduled to meet with that person on July 21 to identify grave and house
locations so they could be "protected as part of the proposed mining
process." Id. Durand advised that, "If either of these
resources are identified within the proposed mine area, an agreement will be
reached with the Choctaw that will allow the development of the mine, while
ensuring that those resources are protected."
Id. at 2. Durand requested
that the Port Bienville site "be retained in the IER 30 review process" until
"IER 30 is ready to enter the public review process." Id.
By letter dated July 23, the contracting officer notified
Durand that, since "the proposed Port Bienville borrow site [had] been denied
further consideration" in IER 30, Durand's revised proposal "is considered
unacceptable." AR, Tab 25, at 2;
AR, Tab 25, at 1, Contracting Officer's Memorandum, July 23, 2009.
By letter dated July 27, the EPCB replied to Durand's July
20 letter, advising that it had reviewed the "new information" provided in the
letter, but that, because of "the significance of the Indian tribal issues
raised and the time to possibly resolve these issues," it was "not possible" to
include the Port Bienville borrow site for consideration in IER 30. Tab 27.
During the remainder of July and August, Durand continued to provide
information to the EPCB, requesting reinstatement of the Port Bienville Site,
or at least a portion of the site that had been included in a prior IER. AR Tabs 28, 30, 31.
Durand challenges the rejection of its proposal on several
grounds. We have considered all of
Durand's arguments and find that they are without merit. We address Durand's primary arguments below.
DISCUSSIONS
Durand asserts that the discussions following evaluation
of offerors' technical proposals were unequal, contrary to the requirements of
Federal Acquisition Regulation (FAR) sect. 15.306(a), since the Corps
discussed CRIR deficiencies with three offerors, but failed to discuss similar
issues with Durand. Protester's Comments
at 12, 14.
The scope and extent of discussions with offerors in the
competitive range are a matter of the contracting officer's judgment. FAR sect. 15.306(d)(3); Biospherics, Inc.,
B‑285065, July 13, 2000, 2000 CPD para. 118 at 5. Although discussions may not be conducted in
a manner that favors one offeror over another, FAR sect. 15.306(e)(1); see
Chemonics Int'l, Inc., B-282555, July 23, 1999, 99-2 CPD para. 61, and
offerors must be given an equal opportunity to revise their proposals,
discussions need not be identical among offerors; rather, discussions are to be
tailored to each offeror's proposal. FAR
sections 15.306(d)(1), (e)(1); WorldTravelService, B‑284155.3, Mar. 26,
2001, 2001 CPD para. 68 at 5-6.
The discussions here were unobjectionable. While, as noted, three offerors were advised
during discussions that their CRIRs contained weaknesses and deficiencies,
Durand's proposal was found acceptable with regard to its CRIR, so the agency
determined that there was nothing in that area to discuss with Durand. AR Tabs 8, 9.
Durand does not assert that its CRIR included information that should
have put the Corps on notice of a problem with its proposed borrow site, and we
find nothing in the record showing that the agency otherwise was or should have
been aware, at the time of discussions, of the problems that came to light
months later. Indeed, as noted above, in
providing the Indian and Mississippi State entities an opportunity to comment
on Durand's proposed borrow site, the EPCB advised that it did not appear that
the site would be problematic. AR Tab
16. Under these circumstances, where the
objections to the proposed site were unknown by the agency--from Durand's
proposal or otherwise--at the time of discussions, there is no basis for us to
find that the discussions with Durand were unequal or otherwise deficient. See Metcalf Constr. Co., Inc.,
B-289100, Jan. 14, 2002, 2002 CPD para. 31 at 5 (although agency informed other
offerors during discussions that their prices exceeded applicable budget
ceilings, agency was not required to discuss budget ceilings with protester,
whose prices did not exceed ceilings at time of discussions); KBM Group,
Inc., B‑281919, B-281919.2, May 3, 1999, 99-1 CPD para. 118 at 10 (agency
did not conduct unequal discussions with awardee and protester where agency
conducted technical discussions with awardee, whose technical proposal was
initially evaluated as containing a number of weaknesses, while conducting no
technical discussions with protester, whose initial proposal was evaluated as
containing no weaknesses).
Durand asserts that the Corps should have contacted Indian
tribes and other interested entities prior to the technical acceptability
determination, which would have then made it possible to raise the objections
with Durand during discussions. However, the description of the technical
evaluation requirements for offerors' CRIRs in section M of the RFP includes no
requirement for, or even mention of, coordination with tribal or state
authorities, and there was nothing elsewhere in the RFP that required the
agency to coordinate with these entities early in the procurement process. Durand cites RFP section L.2.2.2, which sets
forth instructions for offerors, and provides with regard to the CRIR that "The
Government is responsible for all coordination activities with federally
recognized Tribes and State Historic Preservation Officers." Protest at 3-4. However, there is nothing in this provision
indicating the timing for the agency's coordination with the identified
entities. We conclude that this argument
is without merit.
We further note that the evaluation scheme set forth in
the RFP clearly contemplated that offerors' CRIRs would be reviewed twice: first in the evaluation of proposals, RFP at
144 (sect. 4.1b), and subsequently with regard to the determination whether to
include offerors' borrow sites in the IER.
RFP at 145-46 (sect. 5.1.1). The
agency's actions were consistent with the RFP in this regard. To the extent Durand believed that some
earlier review was required, and that this dual review--and the attendant
possibility that a proposal could be rejected based on the results of
either--was improper, the protest is untimely.
Again, the RFP did not provide for a NEPA review early in the
procurement process, and specifically provided for a dual review. Such alleged deficiencies on the face of a
solicitation must be protested prior to the initial closing time. 4 C.F.R. sect. 21.1(a) (2009).
REJECTION OF PROPOSAL
Durand asserts that the rejection of its proposal was
"arbitrary and capricious." Protest at
8-10. It claims that, as a factual
matter, there are no affected historic sites at the Port Bienville site, and
that the Corps improperly declined its offer to adjust the boundaries of the
borrow site and to enter into a prophylactic memorandum of agreement with the
Choctaws. Id. The Corps responds that it reasonably relied
on, and was required to consider, the position taken by the Choctaws, that it
was not required to grant Durand's request to adjust the borrow site, and that
Durand's plan regarding a memorandum of understanding with the Choctaws was
"purely speculative" and therefore not acceptable. AR at 11-13.
In reviewing a protest challenging an agency's proposal
evaluation, it is not our role to reevaluate proposals. Rather, we will consider only whether the
evaluation was reasonable
and consistent with the terms of the solicitation and applicable statutes and
regulations. Anwar Al-Anduols,
B-401550, B-401550.3, Sept. 22, 2009, 2009 CPD para. __ .
The agency reasonably determined that Durand's proposal was
unacceptable. Inclusion of the proposed borrow site in the IER was an
express precondition to an offeror's being eligible for award. RFP at 145-46. While Durand disagrees with the EPCB's
findings, the contracting officer was presented with a conclusive determination
by the EPCB that Durand's site would not be included in the IER, AR, Tab 25,
Contracting Officer's Memorandum, July 23, 2009, and her rejection of the
proposal on this basis was consistent with the RFP. There is no indication in the record that the
contracting officer had any reason to believe that the EPCB's determination was
defective, unsupported, or suspect in any way.
Moreover, the protester's disagreement with the EPCB's determination
notwithstanding, it has not established any error or impropriety in that
determination. Under these
circumstances, the contracting officer reasonably relied on the determination
in rejecting Durand's proposal. See
generally Daisung Co., B-294142, Aug. 20,
2004, 2004 CPD para. 196 (where contracting officer's determination to exclude
offeror from competition was based on information provided by agency audit and
criminal investigation divisions, contracting officer acted properly in relying
on that information, which GAO will not question); John Blood, B-290593,
Aug. 26, 2002, 2002 CPD para. 151 at 4 (contracting officer could rely on past
performance information he had no reason to question); Advanced Commc'n
Sys., Inc., B-283650 et al., Dec. 16, 1999, 2000 CPD para. 3 (agency
reasonably relied on Defense
Contract Audit Agency's advice
in performing cost realism analysis).
To the extent the protester believes the agency should have
delayed the procurement until it had the opportunity to resolve the identified
issues with its borrow site, there simply was no requirement that it do so
after--as we have found--reasonably rejecting the firm's proposal. We note that the EPCB did continue
communications with Durand regarding the Port Bienville site after initially
rejecting the site for inclusion in IED 30, but ultimately declined to change
its determination, concluding there was no indication that a prompt resolution
was at hand or likelihood that its determination would be reversed. See, e.g., AR Tabs 24, 25, 27,
28; COS at 12-13. The agency advises,
unrebutted by the protester, that as of October 23, Durand had not resolved its
issues with the Choctaw tribes and the Mississippi SHPO. Agency Supp. Report at 4. We further note that the contracting officer
determined that any further delay would impact other levee construction
contracts dependent on borrow material obtained under this procurement. COS at 16.
The protest is denied.
Lynn H. Gibson
Acting General Counsel
[1] NEPA regulations allow the use of the NEPA process for section 106 purposes. 36 C.F.R. sect. 800.8(c); AR at 3.








