B-401773, Science Applications International Corporation, November 10, 2009
Decision
Matter of: Science Applications International Corporation
James
J. McCullough, Esq., and Steven A. Alerding, Esq., Fried Frank Harris Shriver
& Jacobson, LLP, for the protester.
Daniel R. Forman, Esq., and Jonathan M. Baker, Esq., Crowell & Moring, for Rapiscan, Inc., an intervenor.
Dennis
J. Gallagher, Esq., Department of State, for the agency.
Mary G. Curcio, Esq., and John M. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Where solicitation limited competition to vendors holding Federal Supply Schedule contract for required items, issuance of purchase order with items not included on successful vendor’s FSS contract was improper.
DECISION
Science Applications
International Corporation (SAIC), of San Diego, California, protests the
Department of State’s issuance of a purchase order to Rapiscan, Inc. under
request for quotations (RFQ) No. S-WHARC-09-Q-0030, issued to vendors holding
General Service Administration (GSA) Federal Supply Schedule (FSS) contracts
for gamma ray vehicle and cargo inspection systems. SAIC asserts that Rapiscan should not have
received the order because certain of the required items were not included
under its FSS contract.
The RFQ was open to manufacturers under GSA FSS 84,
category 426-4K, Metal and Bomb Detection Equipment, and required vendors to
include their FSS contract number in their quotations. RFQ sect. D; Agency Report (AR) at 3. The RFQ included eight line items to be
priced by vendors. The agency issued the
order to Rapiscan based on its lowest-priced, technically acceptable
quotation. SAIC asserts that the order
improperly was issued to Rapiscan because two of the items quoted were not on
Rapiscan’s FSS contract at the time the order was issued.
The agency concedes that two items were not included under
Rapiscan’s FSS contract at the time the order was issued, but principally argues
that, since there was no requirement in the RFQ that all items be on the FSS at
the time quotations were submitted or at the time the order was issued, this
would not be a proper basis for rejecting Rapiscan’s quotation. The agency asserts that the order was
properly issued because the items were added to Rapiscan’s FSS contract before
the required delivery date.
FSS procedures provide agencies a simplified process for
obtaining commonly used commercial supplies and services, Federal Acquisition
Regulation (FAR) sect. 8.401(a), and, although streamlined, satisfy the
requirement for full and open competition.
41 U.S.C. sect. 259(b)(3) (2006); FAR sect. 6.102(d) (3). However, non-FSS products and services may
not be purchased using FSS procedures; their purchase requires compliance with
otherwise applicable procurement laws and regulations, including those
requiring the use of full competitive procedures. Symplicity Corp., B-291902, Apr. 29.
2003, 2003 CPD para. 89 at 4. [1] Where an agency announces its intention to
order from an existing FSS, all items quoted and ordered are required to be on
the vendor’s schedule contract as a precondition to its receiving the order. Tarheel Specialties, Inc., B-298197,
B-298197.2, July 17, 2006, 2006 CPD para. 140 at 4; CourtSmart Digital
Systems, Inc., B-292995.2, B-292995.3, Feb. 13, 2004, 2004 CPD para. 79 at
5; see ATA Def. Indus. v. United States, 38 Fed. Cl. 489 (1997). [2]
Since the solicitation here limited the competition to
vendors holding a specified FSS contract, the agency was limited to issuing the
purchase order to a vendor whose FSS contract included all of the required
items. Tarheel Specialties, Inc.,
supra; CourtSmart Digital Systems, Inc., supra. Since it is undisputed that Rapiscan’s FSS
contract did not include all required items at the time the order was issued,
the order could not properly be issued to Rapiscan. We reject the agency’s position that it was
proper to issue an order to Rapiscan because the ordered items will be added to
its FSS contract prior to the delivery date.
This position ignores our decisions, as well as the Court of Federal
Claims’s decision in ATA, and, since there is no way to determine with
certainty whether a vendor’s FSS contract will include the ordered items in the
future, clearly would undermine, if accepted, the requirement that non-FSS
items be purchased using normal full and open competition procedures.[3]
The agency asserts, alternatively, that the order actually
was issued to Rapiscan on the basis of full and open competition--and that the
non-FSS item rule therefore does not apply--since all participants in the
mobile intrusive gamma inspection unit marketplace hold FSS contracts, and all
were permitted to submit quotations. We
disagree because the agency’s argument is based on a flawed premise. Pursuant to the FAR, full and open competition
is achieved only where all responsible sources are permitted to compete. FAR sect. 2.101.
While the agency asserts that all potential vendors of the required
items were permitted to compete because all hold FSS contracts, there is no
evidence in the record--and we question whether sufficient evidence could be
presented--showing that there are no vendors of the items that do not hold FSS
contracts. Rather, under the
circumstances here, the only way to ensure that all responsible sources are
permitted to compete would be to conduct a competition without FSS
restrictions. Moreover, the agency’s
argument ignores the possibility that some FSS vendors chose not to submit a
quotation because, like Rapiscan, they did not have all of the required items
on their FSS contracts. Notably, in this
regard, the agency reports that only 4 of the 46 FSS vendors notified of the
solicitation requested a copy of it.
Based on the foregoing, we sustain the protest. We recommend that the agency cancel
Rapiscan’s purchase order. Because there
is a dispute in the protest record as to whether SAIC’s FSS contract includes
all required items, we also recommend that the agency determine whether SAIC had
all items on its FSS contract at the time the order was issued. If the agency determines that this is the
case, and that SAIC’s quotation is otherwise technically acceptable and lowest-priced,
the agency should issue a purchase order to SAIC. Otherwise, the agency should issue the
purchase order to the vendor in line for award under the terms of the RFQ, and
in accordance with this decision. We
also recommend that SAIC be reimbursed the costs of filing and pursuing the
protest, including reasonable attorneys’ fees.
4 C.F.R. sect. 21.8(d)(1) (2009).
SAIC should submit its certified claim for costs, detailing the time
expended and cost incurred, directly to the contracting agency within 60
days after receipt of this decision. 4
C.F.R. sect. 21.8(f)(1).
Lynn H. Gibson
Acting General Counsel
[1]We
note that in, in response to our request for its views regarding this same
issue in Symplicity Corp., supra, the General Services
Administration, the agency responsible for administering the FSS program,
expressed a view consistent with our holding there--when an agency conducts a
procurement under the FSS program, all items ordered must be on the vendor’s
FSS contract at the time the order is issued.
[2]
The sole exception to this requirement is for items that do not exceed the
micro‑purchase threshold of $3,000.
See CourtSmart Digital Systems, Inc., supra,
at 5. The items in issue here
exceed the threshold amount.
[3] The agency also argues that it should be sufficient that the ordered items are of the type included on, and within the scope of, the vendor’s FSS contract. However, similarity is not sufficient. Rather, again, the agency properly may issue an order only for items that are included on the vendor’s FSS contract at the time the order is issued. See, Tarheel Specialties, Inc., supra; Symplicity Corp., supra.







